Trillium Valley Park Pond 48
Welcome to the project page for the cleanout and retrofit of Trillium Valley Park Pond 48. Pond 48 was identified for cleanout given the level of sediment accumulation in the pond. Pond 48 was identified as a candidate for retrofit to improve performance and address operational issues. The retrofit of Pond 48 requires the completion of a Schedule B Environmental Assessment to identify and evaluate alternatives for retrofitting the pond and select a preferred alternative to be implemented.
This page will provide information as the project progresses from the Environmental Assessment stage, to the detailed design stage and finally to construction. Project updates will be posted in the newsfeed and the current progress of the project is noted in the project Lifecycle. The page may be open to public comments for limited time periods at key stages of the project, so please check back often or subscribe to follow the project to receive email updates.
Welcome to the project page for the cleanout and retrofit of Trillium Valley Park Pond 48. Pond 48 was identified for cleanout given the level of sediment accumulation in the pond. Pond 48 was identified as a candidate for retrofit to improve performance and address operational issues. The retrofit of Pond 48 requires the completion of a Schedule B Environmental Assessment to identify and evaluate alternatives for retrofitting the pond and select a preferred alternative to be implemented.
This page will provide information as the project progresses from the Environmental Assessment stage, to the detailed design stage and finally to construction. Project updates will be posted in the newsfeed and the current progress of the project is noted in the project Lifecycle. The page may be open to public comments for limited time periods at key stages of the project, so please check back often or subscribe to follow the project to receive email updates.
-
Construction update 5
Share Construction update 5 on Facebook Share Construction update 5 on Twitter Share Construction update 5 on Linkedin Email Construction update 5 linkNote: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
The construction plan for the week of December 16, 2024 :
- Continue with topsoil and tree installation around re-aligned creek.
- Continue to install rocky material over synthetic clay liner for new pond. It will protect the clay liner from damage and provide weight to counteract uplift from groundwater.
- Temporary repair for sidewalk at site entrance.
The contractor will likely be shutting down for winter holidays from December 23 to January 3. Some work may occur based on crew availability.
The plan for construction for the week of January 6, 2025:
- Install armour stone retaining wall around edge of new pond.
Please note that installation of the oil-grit separator on Gatestone Boulevard could not be completed due to unfavourable soil and groundwater conditions. Temporary asphalt and curb has been restored for the winter. Installation of the OGS will likely be completed in the spring using alternative dewatering methods to ensure soil movement doesn’t undermine the nearby roadway.
-
Construction update 4
Share Construction update 4 on Facebook Share Construction update 4 on Twitter Share Construction update 4 on Linkedin Email Construction update 4 linkNote: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
The current plan for construction over the two-week period from November 18 to 29, 2024 is:
- Grade and shape new pond on northeastern portion of site.
- Starting on or about November 21 – landscapers on-site to complete Clair Creek re-alignment work:
- Installing stones for pools and shallow rocky sections.
- Installing wood debris for fish habitat within channel.
- Topsoil and hydroseeding banks of creek.
- Planting trees and shrubs as part of landscaping plan (May need to wait until Spring 2025, depending on plant availability).
- Starting on or about November 27 – Install oil-grit separator in roadway on Gatestone Boulevard.
Please note the installation of the oil-grit separator on Gatestone Boulevard is tentatively delayed until roughly November 27. This is due to delays in the manufacture of the unit. We are working with the manufacturer to accelerate this process as much as possible, so be prepared for a possible earlier start.
The plan remains to maintain a lane of traffic, with flag staff to direct traffic. Due to the potential for traffic backups, it’s advised that residents try to avoid the area if possible.
-
Construction update 3
Share Construction update 3 on Facebook Share Construction update 3 on Twitter Share Construction update 3 on Linkedin Email Construction update 3 linkNote: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
Due to heavy rain on October 29, some work was delayed. The current plan for construction over the two-week period from November 4 to 15, 2024 is:
- Continue consolidating and removing sediment from old farmer’s pond.
- Complete re-grading and re-shaping the southwest portion of the site where the creek will be re-aligned.
- Start landscape restoration work for re-aligned creek (i.e. adding in stone riffles, hydroseeding banks, landscape plantings, adding woody debris habitat areas, etc.)
Please note that installation of the oil-grit separator on Gatestone Boulevard is tentatively scheduled to start on or about Monday November 18, 2024. The current plan is to maintain a lane of traffic, with flag people to direct traffic. Due to the potential for traffic backups, it’s advised residents try to avoid the area if possible.
-
Construction update 2
Share Construction update 2 on Facebook Share Construction update 2 on Twitter Share Construction update 2 on Linkedin Email Construction update 2 linkNote: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
The current plan for construction over the two-week period from October 21 to November 1 is:
- Strip topsoil and haul out remaining brush.
- Consolidation and removal of sediment from old farmer’s pond.
- Complete re-grading and re-shaping the southwest portion of the site where the creek will be re-aligned.
- Start landscape restoration work for re-aligned creek (i.e. adding in stone riffles, hydroseeding banks, landscape plantings, adding woody debris habitat areas, etc.)
-
Construction update 1
Share Construction update 1 on Facebook Share Construction update 1 on Twitter Share Construction update 1 on Linkedin Email Construction update 1 linkNote: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
Construction to date has included tree removal, clearing and grubbing, dewatering of old farmer’s pond with associated fish/wildlife rescue, bypass pumping of creek, isolation of creek with associated fish/wildlife rescue.
The current plan for construction over the two week period from October 7 to 18, 2024 is:
- Consolidation and removal of sediment from old farmer’s pond.
- Decommissioning and removal of existing groundwater monitoring wells on-site.
- Removal of organic sediments and construction of access road through site.
- Start re-grading and re-shaping the portion of the site where the creek will be re-aligned.
-
Notice of construction
Share Notice of construction on Facebook Share Notice of construction on Twitter Share Notice of construction on Linkedin Email Notice of construction linkThe City of Waterloo would like to provide notice that the start of construction for the Pond 48 retrofit and watercourse re-alignment will begin on or about Monday September 16, 2024. The City has retained Musselman Excavating to complete construction. The week of September 16, 2024, Musselman will complete preliminary activities such as moving equipment and materials to site, surveying, and tree removal. Heavier construction is anticipated to begin the week of September 23. Construction will typically occur 7 a.m. to 7 p.m. Monday to Friday.
Select residents will receive notices from a third party, hired by the contractor, to complete pre-construction condition assessments of properties touching the site. These notices will contain contact information to setup an inspection date/time. Inspections consist of taking photos and videos of the interior and exterior of your house to establish a baseline condition in the event that there is a claim for any damages to your property as a result of construction. Residents can choose not to have their property inspected. If you choose not to have your property inspected, it's strongly recommended you take photos yourself in advance of construction.
Updates during construction will be periodically posted on Engage Waterloo, so please subscribe to this webpage for updates.
-
Presentation of design and status update
Share Presentation of design and status update on Facebook Share Presentation of design and status update on Twitter Share Presentation of design and status update on Linkedin Email Presentation of design and status update linkThe detailed design for the retrofit of Pond 48 and re-alignment of Clair Creek is complete and the City is in the process of hiring a contractor for construction. This update will provide information on the final design and what to expect during construction.
Why did it take so long?
The project was started as an Environmental Assessment in 2019, prior to the start of the pandemic. During the early days of the pandemic, the process was slowed as the City’s cash flow was affected by the deferral of tax collection that was implemented. In subsequent years, the city became aware of some major deficiencies at other stormwater management ponds that were causing private property damage. Maintenance of those ponds was prioritized over Pond 48. With those issues behind us, Pond 48 was able to move forward.
Why does Pond 48 need to be retrofitted and the Creek re-aligned?
The details are provided in the Class Environmental Assessment (“EA”) project file report, which can be downloaded from the Documents section of this page. A brief summary is provided below:
- Pond 48 is what’s referred to as an online stormwater management pond. This means that the pond is attached to a stream, in this case Clair Creek.
- Online ponds are generally undesirable as:
- Online ponds can warm up the water in the creek, making it harmful to fish.
- Fish are exposed to the urban pollutants that the pond is supposed to capture
- Online ponds are more expensive to clean due to increased permitting, pumping, and erosion control costs.
- Cleaning an online pond is a significant and undesirable intrusion into Clair Creek.
- Online ponds tend to fill with sediment more quickly, requiring frequent cleanout. The pond was constructed in 1989-1990. Based on aerial imagery of the pond, the pond had disappeared by 1997, suggesting a cleanout frequency of less than 7 years.
- The environmental assessment looked at options to take Pond 48 offline. The preferred solution requires Clair Creek to be re-routed around a newly constructed, offline, Pond 48.
By retrofitting the pond to be offline and re-aligning Clair Creek around the new pond, it will:
- Function better at removing pollutants from urban stormwater runoff.
- Reduce the frequency of cleanout to a level less more acceptable to adjacent residents.
- Reduce environmental damage by not doing construction within Clair Creek.
- Reduce operating costs by reducing planning, permitting and construction costs as well as lower cleanout frequency.
What is a Class Environmental Assessment?
A Class EA is a provincially regulated decision-making process to ensure good planning when a municipality identified opportunities for improvement on infrastructure projects. The process involves identifying a deficiency/opportunity, creating multiple possible design alternatives to address said deficiency, ranking each alternative against social/environmental/economic considerations, presenting the preferred alternative to the public for review, and filing the final report for 30-day public review.
A public information centre meeting was held at the at the John M. Harper branch of Waterloo Public Library on May 8, 2019. Comments provided indicated agreement with Alternative #5 as the preferred alternative. The project report was filed in September 2022, with the 30 day public review period ending October 8, 2022.
Design Details
The design drawings for the reconfigured pond and creek can be downloaded from the Documents Library. The proposed, off-line Pond 48 will be moved slightly to the northwest from it’s former location. It will be enlarged to improve pollutant removal efficiency to a level closer to modern standards. Due to space constraints, the pond can’t be enlarged to the degree required to fully meet modern standards, so an Oil-Grit Separator unit will be installed in Gatestone Boulevard to assist in removing pollutants. Clair Creek will be re-aligned to the west of the new pond. This design will require that the artificial pond to the west of Pond 48 will need to be removed.
Timing
Permits for the project have been obtained from the Department of Fisheries and Oceans as well as the Grand River Conservation Authority. The project is currently out for tender. Once a contractor is procured, an official schedule with start date will be determined with the contractor. It’s estimated that work will begin late August or early September.
Fish and Herpetofauna Handling and Relocation
Fish rescues and relocation of herpetofauna (i.e. reptiles and amphibians) will be completed by personnel holding valid fish and wildlife handling permits from the Ministry of Natural Resources and Forestry (“MNRF”), and in accordance with MNRF Best Management Practices.
Tree Removal and Restoration Planting Plan
The reconfiguration of Pond 48 and Clair Creek will require significant tree removal to enlarge the pond and re-align the creek. Approximately 59 trees are to be removed. Based on the tree survey completed during the EA, nearly half the trees slated for removal are either:
- non-native or invasive (i.e. Manitoba Maple, Norway Maple, Norway Spruce);
- dead Ash trees killed by Emerald Ash borer; and/or
- in poor condition.
At the request of the Manager of Forestry, the City will be installing armour stone retaining walls to preserve three large trees:
- Tree ID 156, Norway Maple. Preserved for it’s size/canopy
- Tree ID 174, Cottonwood. Preserved for it’s size/canopy and rarity in Ontario
- Tree ID 180, Yellow Birch. Preserved for it’s size/canopy.
The armour stone walls will by virtue of their nature preserve additional trees nearby.
A planting plan has been prepared to restore trees and shrubs following construction, which will include over 80 new trees and hundreds and new shrubs. New trees will be native species such as Tamarack, Basswood, Trembling Aspen, Red Maple, Serviceberry, etc. Shrubs will be native species such as redosier dogwood, ninebark, staghorn sumac, elderberry, etc.
Although the initial tree removal and subsequent construction may seem irreparable at first, please note the photos below that show the nearby Chancery Lane pond during and following construction. The photos show how quickly the pond can regain a more natural and aesthetically pleasing appearance:
Photo 1: Chancery Lane pond during construction in Winter 2021.
Photo 2: Chancery Lane pond shortly after landscape restoration in June 2021.
Photo 3: Chancery Lane pond 1 year after landscape restoration in June 2022.
Photo 4: Chancery Lane pond 3 years after landscape restoration in July 2024.
-
Notice of Completion and 30-day review
Share Notice of Completion and 30-day review on Facebook Share Notice of Completion and 30-day review on Twitter Share Notice of Completion and 30-day review on Linkedin Email Notice of Completion and 30-day review linkThe 30-day public review period for the study ended on October 8, 2022. The documents remain available for viewing, but the official commenting period for the Project File Report is finished. The city and our engineering consultant will review any comments received and begin the detailed design and approvals process.
The city is pleased to announce that it has completed a retrofit assessment of Trillium Valley Park Pond 48. The project has been completed in accordance with the Municipal Engineers Association Municipal Class Environmental Assessment document (October 2000, as amended in 2007 and 2011), which is an approved process under the Ontario Environmental Assessment Act. Pond 48 has been completed as a Schedule ‘B’ project, which involves a greater degree of study and public consultation, including the completed PIC to present the project to the public and seek input on the identified preferred solution.
A Project File Report has been prepared, which documents; the planning and design process, how public, regulatory agency input was addressed, the evaluation and selection of the preferred solution, along with associated mitigation measures to address impacts, and next steps towards project implementation.
The filing of this report completes the planning and conceptual design stage of the project. By way of this notice, the report is placed on record for a 30-day public review period starting on September 8, 2022 and ending on October 8, 2022.
Lifecycle
-
May 2018
Trillium Valley Park Pond 48 has finished this stageNotice of commencement delivered to residents. Start natural heritage study field activities.
-
October 2018
Trillium Valley Park Pond 48 has finished this stageNatural heritage field activities complete.
-
May 2019
Trillium Valley Park Pond 48 has finished this stageIn-person public information session.
-
September/October 2022
Trillium Valley Park Pond 48 has finished this stageNotice of completion. Project file report posted for 30-day review
-
October 2022
Trillium Valley Park Pond 48 has finished this stageStart detailed design
-
July/August 2024
Trillium Valley Park Pond 48 has finished this stageHire contractor.
-
Early September 2024
Trillium Valley Park Pond 48 is currently at this stageStart construction.
-
Late December 2024
this is an upcoming stage for Trillium Valley Park Pond 48Complete construction.
-
Spring 2025
this is an upcoming stage for Trillium Valley Park Pond 48Final landscaping.
Project Team
-
GV
Phone 519-886-1550 x78066 Email gavin.vermeer@waterloo.ca -
MS
Phone 905-335-2353 x3080 Email matt.senior@wsp.com