Construction update 3

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.

Due to heavy rain on October 29, some work was delayed. The current plan for construction over the two-week period from November 4 to 15, 2024 is:

  • Continue consolidating and removing sediment from old farmer’s pond.
  • Complete re-grading and re-shaping the southwest portion of the site where the creek will be re-aligned.
  • Start landscape restoration work for re-aligned creek (i.e. adding in stone riffles, hydroseeding banks, landscape plantings, adding woody debris habitat areas, etc.)

Please note that installation of the oil-grit separator on Gatestone Boulevard is tentatively scheduled to start on or about Monday November 18, 2024. The current plan is to maintain a lane of traffic, with flag people to direct traffic. Due to the potential for traffic backups, it’s advised residents try to avoid the area if possible.

Share Construction update 3 on Facebook Share Construction update 3 on Twitter Share Construction update 3 on Linkedin Email Construction update 3 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>