Construction update 2

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.

The current plan for construction over the two-week period from October 21 to November 1 is:

  • Strip topsoil and haul out remaining brush.
  • Consolidation and removal of sediment from old farmer’s pond.
  • Complete re-grading and re-shaping the southwest portion of the site where the creek will be re-aligned.
  • Start landscape restoration work for re-aligned creek (i.e. adding in stone riffles, hydroseeding banks, landscape plantings, adding woody debris habitat areas, etc.)