Construction update 4
Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
The current plan for construction over the two-week period from November 18 to 29, 2024 is:
- Grade and shape new pond on northeastern portion of site.
- Starting on or about November 21 – landscapers on-site to complete Clair Creek re-alignment work:
- Installing stones for pools and shallow rocky sections.
- Installing wood debris for fish habitat within channel.
- Topsoil and hydroseeding banks of creek.
- Planting trees and shrubs as part of landscaping plan (May need to wait until Spring 2025, depending on plant availability).
- Starting on or about November 27 – Install oil-grit separator in roadway on Gatestone Boulevard.
Please note the installation of the oil-grit separator on Gatestone Boulevard is tentatively delayed until roughly November 27. This is due to delays in the manufacture of the unit. We are working with the manufacturer to accelerate this process as much as possible, so be prepared for a possible earlier start.
The plan remains to maintain a lane of traffic, with flag staff to direct traffic. Due to the potential for traffic backups, it’s advised that residents try to avoid the area if possible.