Construction update 7

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change, and residents should be prepared for unexpected changes.

The current plan for construction over the two-week period from November 18 - 29, 2024 is:

  • Phase 1 – Moore Ave S
    1. Line painting (concurrent with Phase 2 line painting).
    2. Installing/reinstalling signage (concurrent with Phase 2).
  • Phase 2 – Waterloo St
    1. Place 'Granular A' road base.
    2. Raise structure lids to base asphalt level.
    3. Paving (tentatively November 21 or 22).
    4. Asphalt driveway paving.
    5. Topsoil, sod and landscaping.
    6. Line painting and signage.

Currently, residents should expect leaf pickup to occur late in the last week of November. An exact date will be provided in mailed out notices and on Engage Waterloo once a date has been set. Please note that new sod may be placed prior to leaf pickup. Given the time of year, the new sod should not be walked on between placement and Spring 2025 to allow for rooting. Please keep this in mind when moving leaves to the curb and street for removal.