Construction update 6
Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change, and residents should be prepared for unexpected changes.
The current plan for construction over the two-week period from November 4 to November 15, 2024 is:
-
Phase 1 – Moore Ave S
- Line painting.
- Installing/reinstalling signage.
- Above items were to have been done over the previous 2-week period, but certain material and design details needed to be addressed first.
-
Phase 2 – Waterloo St
- Pour curb (tentatively Monday, November 4).
- Form and pour sidewalk.
- Form and pour concrete driveway aprons and restore concrete driveways and walkways.
- Place granular A road base.
- Raise structure lids to base asphalt level.
Share Construction update 6 on Facebook
Share Construction update 6 on Twitter
Share Construction update 6 on Linkedin
Email Construction update 6 link