Construction update 5
Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
The current plan for construction over the two week period from October 21 to November 1 is:
- Phase 1 – Moore Ave S
- Line painting
- Installing/reinstalling signage
- Phase 2 – Waterloo St
- Final connections for new watermain
- Begin removing existing soil and building new road base
- Curbs, sidewalks and driveway aprons