Construction update 3

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.

The current plan for construction over the two week period from September 23 to October 4 is:

  • Phase 1 – Moore Ave S
    1. Start forming and pouring concrete sidewalks, driveway aprons and driveways.
    2. Place and compact granular material road base between curbs.
    3. Possibly asphalt paving by October 4, 2024.
  • Phase 2 – Waterloo St
    1. Continue replacement of water and sanitary service laterals to property line for each house.
    2. Start process of commissioning new watermain.
    3. Start replacement of storm sewer.

Once concrete curb, sidewalk and driveway aprons start being poured in Phase 1, residents won’t be able to enter their driveways during evenings or weekends for a period of a couple weeks. This is due to the need to let concrete dry for several days before driving on it and the staggered nature of installation.