Construction update 2

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.

The current plan for construction from September 9 - 20, 2024 is:

  • Phase 1 – Moore Ave S
    1. Pending successful commissioning of new watermain, connect new watermain to existing watermain at limits of work.
    2. Disconnect services from temporary watermain and connect to new watermain
    3. Placement of concrete curb.
    4. Start forming and pouring concrete sidewalks and driveway aprons.
  • Phase 2 – Waterloo St
    1. Continue and finish replacement of sanitary sewer.
    2. Start replacement of water and sanitary service to property line for each house.

Once concrete curb, sidewalk and driveway aprons start being poured in Phase 1, residents won’t be able to enter their driveways during evenings or weekends for a couple weeks. This is due to the need to let concrete dry for several days before driving on it and the staggered nature of installation.

Share Construction update 2 on Facebook Share Construction update 2 on Twitter Share Construction update 2 on Linkedin Email Construction update 2 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>