St. George Street: Benton Street to Queen Street South
As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff have scheduled road and sewer improvements in your neighbourhood on the street(s) listed above.
These improvements have begun. You will be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.
The specific improvements scheduled for this street are:
- Upgrade the existing storm sewer, sanitary sewer and water mains, including additional hydrants
- Upgrade existing storm sewer, sanitary sewer & water mains, including additional hydrants as required
- Replace existing sanitary and water services from the new mains to the property line
- Curb and gutter, and sidewalks will be installed
- Upgrade the asphalt roadway
- Replace all driveway ramp entrances in concrete
- Install and/or replace retaining walls
These improvements are being done to upgrade the existing, deteriorated underground services and above-ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.
How you may be affected
In order to carry out these improvements, it will be necessary to close this street to through traffic. Prior to any road closure, signs will be posted on the approaching streets advising motorists of the date and the duration of the closure.
For more details on how this construction may affect you, please read the information package
For more information, all residents are also invited to view the project information boards
Stay informed
Progress and major milestones will be posted on this project page. Subscribe to get project updates. Add your email to the Stay Informed section and click 'Subscribe'.
As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff have scheduled road and sewer improvements in your neighbourhood on the street(s) listed above.
These improvements have begun. You will be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.
The specific improvements scheduled for this street are:
- Upgrade the existing storm sewer, sanitary sewer and water mains, including additional hydrants
- Upgrade existing storm sewer, sanitary sewer & water mains, including additional hydrants as required
- Replace existing sanitary and water services from the new mains to the property line
- Curb and gutter, and sidewalks will be installed
- Upgrade the asphalt roadway
- Replace all driveway ramp entrances in concrete
- Install and/or replace retaining walls
These improvements are being done to upgrade the existing, deteriorated underground services and above-ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.
How you may be affected
In order to carry out these improvements, it will be necessary to close this street to through traffic. Prior to any road closure, signs will be posted on the approaching streets advising motorists of the date and the duration of the closure.
For more details on how this construction may affect you, please read the information package
For more information, all residents are also invited to view the project information boards
Stay informed
Progress and major milestones will be posted on this project page. Subscribe to get project updates. Add your email to the Stay Informed section and click 'Subscribe'.
-
Sod placement
Share Sod placement on Facebook Share Sod placement on Twitter Share Sod placement on Linkedin Email Sod placement linkThis work is part of the Council-approved Capital Budget to renew aging city roads, sanitary sewers, storm sewers, watermains, and sidewalk for current and future needs. See the map of the work area below.
Please take note of this letter’s date, as there will be a follow-up notice delivered at the time of sod acceptance and handover at the end of the sod placement limited warranty end date.
Map of work area
What to expect during construction
Work hours
Work will take place from 7 a.m.to 7 p.m., Monday to Friday. Work on weekends may also be required from time to time, but is unlikely, and is pre-approved Saturday and Sundays from 7 a.m. to 7 p.m.
Restoration
The construction work area will be restored with sod, concrete and/or asphalt where required. Interlocking bricks, flagstone on a granular base, or other similar features that are removed from public and private property during construction will be replaced.
Sod 60-day placement limited warranty end date: June 14, 2025
The contractor is responsible for the following items within the first 60-days after placed, which include:
- Installation of topsoil and sod including rolling of the sod
- Watering of the sod immediately after placement, and during the 60-day warranty period.
- First cut of the sod within 14 days after placement
An inspection will be completed by the project team just before the end of the 60-day limited warranty period.
Contractor watering truck
The contractor is responsible to water the newly placed sod during the first 60 days after placement. The contractor will typically water by way of water truck. On-street parked vehicles on the roadway during watering does impede and limit the watering truck’s access and ability to water boulevards. We kindly ask to limit parking on the street after sod is placed.
Winter dormant period
Depending on the time of year the sod is placed, there is a winter dormant period where the 60-day placement limited warranty is suspended. This is during the period of November 15 to April 15, inclusive. The sod 60-day placement limited warranty would restart after this dormant period elapses. Please see above for the sod limited warranty end date.
Resident watering
We encourage residents and property owners to continue watering throughout the sod warranty period and after the sod is accepted (according to the Region of Waterloo water use by-law). Working together on watering will help the sod to establish and give it the best chances.
Lawn mowing and grass cutting
Aside from the Contractor’s first cut taking place within 14 days of sod placed, it is the responsibility of the resident or property/business owner to continue to always cut and maintain the grass. It must be a height of 75mm (or 3 inches) and not any shorter. We encourage you to raise your mower height to the highest possible, as this helps the new sod continue to grow. It also gives it the best chance to survive through hot weather over the course of the next 2 years. Cutting the lawn too short will void any sod warranty immediately.
Fertilizer, aeration and overseeding
A year after the installation of sod, in springtime the contractor is responsible to fertilize, aerate and overseed the newly sodded areas from the previous construction year.
Sod inspection and handover
The city will inspect the condition of the newly sodded area at the end of 60 days. The contractor will be required to replace any deteriorated sod noted at the time of inspection. After this inspection and the replacement of any deteriorated sod, the care and maintenance of the sod will be handed over to become the resident or property/business owner’s responsibility. To find out best practices for sod care and maintenance, please visit the Nursery Sod Growers Association of Ontario.
Site Inspector
If you have construction questions or an issue onsite, we ask that you contact the Site Inspector who represents the City onsite. The Site Inspector is onsite daily and can be identified by the white hardhat they wear with either the city logo or consultant company logo on it.
Need more information?
If you have questions about the upcoming work, please contact us.
City Project Manager
Licinio Costa
226-749-3034 (TTY:1-866-969-9994)
Engineering General inquiries
519-741-2406
Thank you for your continued patience. We are working towards building better infrastructure.
-
Surface Works Notice Nov. 7 to 8
Share Surface Works Notice Nov. 7 to 8 on Facebook Share Surface Works Notice Nov. 7 to 8 on Twitter Share Surface Works Notice Nov. 7 to 8 on Linkedin Email Surface Works Notice Nov. 7 to 8 linkThe City of Kitchener will reconstruct the road on St. George Street (Queen Street to Benton Street) Nov. 7 and 8. Bel-Air Excavating and Grading Limited the contractor is installing new concrete curb, sidewalk, and driveway ramps.
The ongoing concrete work will limit driveway access. Residents will be required to park on side streets in permitted areas if issued parking passes or we will try and complete works in two stages to possibly permit access.
This work is part of the Council-approved 2024 Capital Works Program to renew aging city roads, sanitary sewers, storm sewers, watermains, and sidewalk for current and future needs. Please see a map of the work area below. Impacts to property access is expected during surface work construction, please see below for more information.
Map of work area
What to expect during surface work construction
Work hours
Work will take place from 7 a.m.to 7 p.m., Monday to Friday. Work on weekends may also be required from time to time, but is unlikely, and is pre-approved Saturday and Sundays from 7 a.m. to 7 p.m.
Driveway access during surface work
The contractor estimates that driveway access will be lost for about 3-5 weeks while concrete curb and gutter, concrete sidewalk, concrete driveway ramps and asphalt road paving is planned to occur. The duration of lost driveway access is due to several factors including:
- time required for crews to complete their work
- time required for concrete to properly cure to reach its proper strength
- subcontractor’s schedule
- other unforeseen factors such as weather
Road and sidewalk access
To complete the work safely, there will be road and sidewalk restrictions within the work zone. Access for emergency vehicles will be maintained at all times. The contractor may construct wood planks/bridges over the newly poured concrete sidewalks at various points along the site to provide pedestrian access to properties.
Driveway access
The contractor will notify you of any temporary restrictions to your driveway access. Due to the nature of the work, driveway access may not be possible at all times.
During reconstruction, temporary parking permits will be issued to displaced residents to allow on-street parking when needed. The permits will list streets for parking options where you can park longer than 3 hours and overnight. The site inspector will hand out the permits. Typically, two permits are handed out per property. If you require additional permits, please reach out to the site inspector.
Permits are to be displayed on the dash of your vehicle. Ensure that your vehicle is parked in permitted areas only and that you do not interfere with any construction operations.
We communicate with the Bylaw Enforcement team to ensure residents displaced by construction are noted, although illegal parking and/or safety related issues will continue to be enforced.
Accessible accommodation
The City's contractor must ensure safe and accessible walkways and entryways are maintained for everyone during construction. Any temporary access disruptions will be communicated as soon as possible. If you experience a disruption, have a specific access need or related accommodation request, contact the person listed below.
Residents who require accommodation (examples: for level entry, longer notice) must contact the Project Manager to arrange for access during construction.
On-site communication
Sometimes, contractors need to communicate with homeowners about what is happening on-site. This could be about driveway access, water shut-offs, pre-construction inspections, and site restoration work (examples: landscaping, installing pavers). The contractor's staff will be identifiable by their high-visibility company branded clothing. If you need to speak with staff on the construction site, please ask for the Site Inspector.
Garbage and recycling
Please have materials placed at curbside before 7 a.m. on your collection day. If required, the contractor will move bins to an appropriate location and return them in reasonable amount of time after collection. Please ensure that you label your bins with your address.
Restoration
The construction work area will be restored with sod, concrete and/or asphalt where required. Interlocking bricks, flagstone on a granular base, or other similar features that are removed from public and private property during construction will be replaced. Further information notice regarding sod will follow once the sod is placed.
Parking
This project will affect on-street parking. Parking in the active work zone is not permitted as space is needed for construction equipment and materials. If your parked vehicle affects construction work, it will be relocated with no charge to the owner.
If you require parking enforcement, please contact 519-741-2345.
Moving in/out and deliveries
Efforts will be made to accommodate properties that have scheduled move-ins / move-outs and deliveries. Please contact the site inspector in advance to advise of any delivery access.
Site Inspector
If you have construction questions or an issue onsite, we ask that you be directed to the site inspector who represents the city onsite. The site inspector is onsite daily and can be identified by the white hardhat they wear with either the city logo or consultant company logo on it.
Jeff Gruber
519-504-1811
If the site inspector is unavailable, please contact the Project Manager listed at the end of this notice.
Need more information?
If you have questions about the upcoming work, please contact us.
City Project Manager
Licinio Costa
226-749-3034 (TTY:1-866-969-9994)
Engineering General inquiries
519-741-2406
Thank you for your continued patience.
-
Construction begins Sept. 16, 2024
Share Construction begins Sept. 16, 2024 on Facebook Share Construction begins Sept. 16, 2024 on Twitter Share Construction begins Sept. 16, 2024 on Linkedin Email Construction begins Sept. 16, 2024 linkThe City of Kitchener will reconstruct the road on St. George Street (Queen Street to Benton Street). Bel-Air Excavating and Grading Limited was awarded the contract for reconstruction work, which is scheduled to start on/or about September 16, 2024.
This work is part of the Council-approved 2024 Capital Works Program to renew aging city roads, sanitary sewers, storm sewers, watermains, and sidewalk for current and future needs. Please see a map of the work area below.
Property impacts are expected, including planned water shut-offs, excavation pits and limited parking. For the duration of the construction, affected properties will receive water via a temporary water supply system.
If you would like to receive updates for this project, please subscribe and you will be added to the email list. Add your email to the Stay Informed box on this page and click 'Subscribe'.
Map of work area
What to expect during construction
Work hours
Work will take place from 7 a.m.to 7 p.m., Monday to Friday. Work on weekends may also be required from time to time, but is unlikely, and is pre-approved Saturday and Sundays from 7 a.m. to 7 p.m.
Construction noise
You may experience intermittent noise and vibration during construction (from vacuum trucks, excavators, dump trucks, power generators, air compressors, paving equipment, concrete equipment, and other machinery).
Pre-condition inspection of structures
On heavy construction projects, the City of Kitchener’s standard practice is to offer to inspect any buildings that might be affected by construction activities before construction starts. If residents or tenants experience any concerns with their property during or after construction, the information from the pre-construction inspection will prove very helpful in quickly and accurately resolving any claims, should they arise.
The City-hired contractor may need access to your house or building to complete a pre-condition inspection survey. The pre-condition inspection survey company named DBA Services Inc. will deliver a pre-construction survey request to schedule a time to complete the survey.
The contractor will not show up asking for entry without prior notice. If you have questions or concerns regarding the identity of the contractor or contractor worker, please contact the person by the contact information at the bottom of this notice.
On-site communication
Sometimes, contractors need to communicate with homeowners about what is happening on-site. This could be about driveway access, water shut-offs, pre-construction inspections, and site restoration work (examples: landscaping, installing pavers). The contractor's staff will be identifiable by their high-visibility company branded clothing. If you need to speak with staff on the construction site, please ask for the Site Inspector.
Accessible accommodation
The City's contractor must ensure safe and accessible walkways and entryways are maintained for everyone during construction. Any temporary access disruptions will be communicated as soon as possible. If you experience a disruption, have a specific access need, or a related accommodation request, contact the person listed below.
Residents who require accommodation (examples: for level entry, longer notice) must contact the Project Manager to arrange for access during the construction period.
Water service disruptions
The water to your property will need to be shut off to allow for connection and disconnection to the temporary water supply. The contractor will provide at least 48-hour advance notice for all planned shut-offs.
If you did not receive advance notice and your water was turned off, an emergency water shut-off may have been necessary to complete the work.
Telephone and internet services
For individual properties, this work may affect phone and internet cables that are not buried deep below the sidewalk. The contractor will coordinate with utility companies to minimize disruption. Residents who find their service has been disrupted should notify their phone or internet service provider immediately to start the repair process.
Important information for owners of sprinkler systems, heated driveways, or private landscaping features
Property owners should remove items located within City property limits (boulevard) to avoid damage. This includes items such as landscaping (plants and pavers), decorative objects, sprinkler systems or heated driveways. If you have a sprinkler system or heated driveway, please contact the Project Manager listed below.
Road and sidewalk access
To complete the work safely, there will be road and sidewalk restrictions within the work zone. Access for emergency vehicles will be maintained at all times.
Driveway access
The contractor will notify you of any temporary restrictions to your driveway access. Due to the nature of the work, driveway access may not always be possible.
During reconstruction, temporary parking permits will be issued to displaced residents to allow on-street parking when needed. The permits will list streets for parking options where you can park longer than 3 hours and overnight. The site inspector will hand out the permits. Typically, 2 permits are handed out per property. If you require additional permits, please reach out to the Site Inspector.
Display the permit on your vehicle’s dash. Park your vehicle only in permitted areas and ensure that you do not interfere with any construction operations.
We communicate with the Bylaw Enforcement team to ensure residents displaced by construction are noted, although illegal parking and safety-related issues will continue to be enforced.
Parking
This project will affect on-street parking. Parking in the active work zone is not permitted as space is needed for construction equipment and materials. If your parked vehicle affects construction work, it will be relocated without charge to the owner.
If you require parking enforcement, please contact 519-741-2345.
Traffic management
Efforts have been made to manage traffic in the area for the safety of workers, road users and residents. Road users should expect delays and increased traffic on nearby main and side streets.
Moving in/out and deliveries
Efforts will be made to accommodate properties that have scheduled move-ins / move-outs and deliveries. Please contact the site inspector in advance to advise of any delivery access.
Garbage and recycling
Please have materials placed at curbside before 7 a.m. on your collection day. If required, the contractor will move bins to an appropriate location and return them in reasonable amount of time. Please ensure that you label your bins with your address.
Restoration
The construction work area will be restored with sod, concrete and/or asphalt where required. Interlocking bricks, flagstone on a granular base, or other similar features that are removed from public and private property during construction will be replaced. Further information notice regarding sod will follow once the sod is placed.
Site Inspector
If you have construction questions or an issue onsite, we ask that you contact the site inspector who represents the city onsite. The site inspector is onsite daily and can be identified by the white hardhat they wear with either the city logo or consultant company logo on it.
Jeff Gruber
519-504-1811
If the site inspector is unavailable, please contact the Project Manager listed below.
Need more information?
If you have questions about the upcoming work, please contact us.
City Project Manager
Licinio Costa
226-749-3034 (TTY:1-866-969-9994)
Engineering General inquiries
519-741-2406
Thank you for your continued patience.
-
Answer our Resident/Owner Questionnaire by June 23
Share Answer our Resident/Owner Questionnaire by June 23 on Facebook Share Answer our Resident/Owner Questionnaire by June 23 on Twitter Share Answer our Resident/Owner Questionnaire by June 23 on Linkedin Email Answer our Resident/Owner Questionnaire by June 23 linkAs part of the City of Kitchener’s ongoing efforts to provide consistent and reliable service, we have scheduled road and sewer improvements in your neighbourhood on St. George Street from Benton Street to Queen Street South.
These improvements are scheduled to begin later this year, with an estimated completion date of fall 2024. Once a schedule for construction has been confirmed you will be notified. You will also be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.
In order to help us address any specific issues or considerations, we ask that you please complete the Resident/Owner Questionnaire. If you have any plans to redevelop your property (for example severance or additional units), please let us know so that we can coordinate any proposed changes with the new roadwork. The survey closes June 23, 2024.
If you live within the project limits and are interested in connecting private storm drains that accept sump pump discharge, you will also be prompted to complete the Storm Service Survey on the last past of the questionnaire.
If you or someone within the project limits would prefer a paper version of the questionnaire, please contact the Engineering division at engineering@kitchener.ca or 519-741-2345.
Follow Project
Lifecycle
-
Project Announced
St. George Street: Benton Street to Queen Street South has finished this stagePlease review this page for information about this upcoming road reconstruction project
-
Questionnaire Open
St. George Street: Benton Street to Queen Street South has finished this stagePlease answer our resident/owner questionnaire, which helps us design the reconstruction project while taking your circumstances into consideration
-
Review and Preparation
St. George Street: Benton Street to Queen Street South has finished this stageWe are reviewing the questionnaire results and preparing for the reconstruction of this road
-
Under Construction
St. George Street: Benton Street to Queen Street South is currently at this stageConstruction is now underway on this street
-
Project Complete
this is an upcoming stage for St. George Street: Benton Street to Queen Street SouthThis road reconstruction project is finished
Report an issue
Call us 24 hours a day 7 days a week to report an issue with construction on your street
- Phone: 519-741-2345
- TTY: 1-866-969-9994
Who's Listening
-
Phone 519-783-8314 Email licinio.costa@kitchener.ca -
Phone 519-783-8306 Email steve.allen@kitchener.ca -
Phone 519-783-8308 Email yam.bhattachan@kitchener.ca
Road reconstructions help Kitchener adapt to climate change
Replacing outdated stormwater pipes and adding green infrastructure during road construction makes Kitchener more resilient to future flooding caused by climate change. This road reconstruction project is funded in part by the Government of Canada. For more information about the City of Kitchener's partnership with the Government of Canada through the Disaster Mitigation and Adaptation Fund, visit kitchener.ca/Stormwater
Soak up rain and reduce runoff
Kitchener has partnered with Reep Green Solutions to help you make changes to beautify your yard and reduce runoff. To learn more and see if you qualify for a free, on-site consultation with a landscape designer, visit Reep's Rain Smart Neighbourhoods.