Update - November 17, 2021

Winter Shutdown:

Snyder's Road reopened to 2 way travel from Gingerich Road to Foundry Street on November 15. The Contractor is still onsite completing various tasks before vacating site for the winter season, however is doing so under single lane closures utilizing flaggers.

Notices, have been delivered to those directly adjacent or in the close proximity to the construction, however if you did not receive one please find a copy (click here for letter) .

The map below shows the contract limits and and timing/status for each stage of construction within the 2021/2022 seasons.

Details of what work was completed or will be completed in each of the stages above can be found in the letter linked above.

A couple of important reminders to residents:

Concrete Separated Cycling Lanes

Residents should note that the newly separated cycling facility installed on both sides of Snyder’s Road is NOT to be used to park vehicles on at any time.

Sidewalk Clearing

A reminder from the Township that all property owners are required to remove snow and ice from sidewalks adjacent to their property within 24 hours of a winter storm.

More information can be found at: https://www.wilmot.ca/en/living-here/Snow-Removal.aspx

Contact Information during winter season

GENERAL ROAD INFORMATION

Region of Waterloo Call Centre

Township of Wilmot

(519) 575-4400

(519) 634-8444


PROJECT SPECIFIC RELATED INQUIRIES

Chris Powell – WalterFedy

Josh Eldridge - WalterFedy

(226) 748-3035

(226)-808-4678

cpowell@waterfedy.com

jeldridge@waterfedy.com

Ken Brisbois – Region of Waterloo

(519) 240-2995

kbrisbois@regionofwaterloo.ca


Letters will be delivered prior to construction commencing in the spring of 2022 to update timing, contacts as well as provide details of the work. The spring start-up letter and any other project specific notices may be posted on this site so residents are encouraged to please check regularly.

We would like to say thank you to all residents and businesses in the construction area for being so patient understanding during the 2021 construction season as this project reaches a step towards it's ultimate completion.

Enjoy the holiday season and stay safe.