FAQs
Where are we with this project?
Since the last public consultation, and before making a final recommendation, the project team reviewed the need for sidewalks on both sides of the new bridge, and whether a sidewalk on one side would adequately serve the needs of those using the sidewalk.
After looking at usage, active transportation needs, and costs to build and maintain, the project team is recommending one sidewalk on the east side of the bridge and is sharing this information with the public through the EngageWR project page.
What are the recommended improvements so far?
The recommended improvements to date include Alternative Alignment #2 which is a staged construction to the west side of the existing structure.
Will the bridge be closed during construction?
No – The proposed Alternative Alignment #2 allows for the existing bridge to be replaced in a staged manner by realigning the bridge and roadway approaches to the west side of the existing structure which will allow two-way travel to be maintained during the work.
What are the next steps?
Pending project approval by Regional Council this summer, we’ll move to detailed design and property acquisition, and plan for construction to start in spring of 2025.