Olympic Drive: Pattandon Avenue to Hoffman Street

Share Olympic Drive: Pattandon Avenue to Hoffman Street on Facebook Share Olympic Drive: Pattandon Avenue to Hoffman Street on Twitter Share Olympic Drive: Pattandon Avenue to Hoffman Street on Linkedin Email Olympic Drive: Pattandon Avenue to Hoffman Street link
Map of project limits

As part of the City of Kitchener’s ongoing efforts to provide consistent and reliable service, we have scheduled road and sewer improvements in your neighbourhood on the street(s) listed above.

These improvements are scheduled to begin, around April 2025, with an estimated completion around October 2025. You will be notified closer to the date construction is scheduled to start on your section of the street, as well as how long access to your driveway will be affected.

The specific improvements scheduled for this street are:

  • Upgrade the existing storm sewer, sanitary sewer and water mains, including additional hydrants as required.
  • Replace existing sanitary and water services from the new mains to the property line.
  • Curb and gutter, and sidewalks will be installed.
  • Upgrade the asphalt roadway.
  • Replace all driveway ramp entrances in concrete.
  • Install and/or replace retaining walls.

These improvements will upgrade the existing, deteriorated underground services and above-ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.

For more information, please review the project information boards

How you may be affected

In order to carry out these improvements, it will be necessary to close this street to through traffic. Prior to any road closure, signs will be posted on the approaching streets advising motorists of the date and the duration of the closure.

Pedestrian access will be maintained to all properties at all times and vehicular access to all properties within the construction area will be maintained for as long as possible. On-street parking permits, which will allow parking on adjacent side streets, will be hand-delivered to affected homes before vehicular access is cut off.

For more details about how this construction may affect you, please read the Information Package

Progress and major milestones will be posted on this project page. Subscribe to get project updates by using the Stay Informed 'Subscribe' button above.


As part of the City of Kitchener’s ongoing efforts to provide consistent and reliable service, we have scheduled road and sewer improvements in your neighbourhood on the street(s) listed above.

These improvements are scheduled to begin, around April 2025, with an estimated completion around October 2025. You will be notified closer to the date construction is scheduled to start on your section of the street, as well as how long access to your driveway will be affected.

The specific improvements scheduled for this street are:

  • Upgrade the existing storm sewer, sanitary sewer and water mains, including additional hydrants as required.
  • Replace existing sanitary and water services from the new mains to the property line.
  • Curb and gutter, and sidewalks will be installed.
  • Upgrade the asphalt roadway.
  • Replace all driveway ramp entrances in concrete.
  • Install and/or replace retaining walls.

These improvements will upgrade the existing, deteriorated underground services and above-ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.

For more information, please review the project information boards

How you may be affected

In order to carry out these improvements, it will be necessary to close this street to through traffic. Prior to any road closure, signs will be posted on the approaching streets advising motorists of the date and the duration of the closure.

Pedestrian access will be maintained to all properties at all times and vehicular access to all properties within the construction area will be maintained for as long as possible. On-street parking permits, which will allow parking on adjacent side streets, will be hand-delivered to affected homes before vehicular access is cut off.

For more details about how this construction may affect you, please read the Information Package

Progress and major milestones will be posted on this project page. Subscribe to get project updates by using the Stay Informed 'Subscribe' button above.


  • CLOSED: This survey has concluded.

    This survey will ask you about things we may need to consider when planning this road reconstruction. It will also ask you whether you are interested in a storm drain connection. 

    We appreciate your cooperation. A city staff member may contact you if we need more information about your comments.

    If you have any questions, contact Steve Allen, Engineering Manager, at steve.allen@kitchener.ca or 519-741-2200 x7584