Photo showing the existing layout of Myers RoadThe Region of Waterloo is working to improve Myers Road from Water Street to Branchton Road, in the City of Cambridge.

This project will:

  • Address the deteriorated pavement condition.
  • Urbanize the corridor with storm sewer and curbs to improve drainage and help reduce traffic speeds.
  • Improve cycling and pedestrian facilities.

Engagement
The first public engagement (Public Consultation Centre) for this project was held in April 2019, at which time we presented a preferred design and asked for public input. At the second public meeting in 2021, we shared the preferred design concept for Myers Road based on feedback received from the first public consultation. The Information Package and drawings showing the Preferred Design Concept are available in the Document Library.

Project Updates

We'll share information as we move forward on this project. The most recent update is available under the Project Update tab below.

This project supports the Region of Waterloo's strategic focus area(s):

Photo showing the existing layout of Myers RoadThe Region of Waterloo is working to improve Myers Road from Water Street to Branchton Road, in the City of Cambridge.

This project will:

  • Address the deteriorated pavement condition.
  • Urbanize the corridor with storm sewer and curbs to improve drainage and help reduce traffic speeds.
  • Improve cycling and pedestrian facilities.

Engagement
The first public engagement (Public Consultation Centre) for this project was held in April 2019, at which time we presented a preferred design and asked for public input. At the second public meeting in 2021, we shared the preferred design concept for Myers Road based on feedback received from the first public consultation. The Information Package and drawings showing the Preferred Design Concept are available in the Document Library.

Project Updates

We'll share information as we move forward on this project. The most recent update is available under the Project Update tab below.

  • August 2024 Update

    Share August 2024 Update on Facebook Share August 2024 Update on Twitter Share August 2024 Update on Linkedin Email August 2024 Update link

    We will be installing a raised pedestrian crossing on Myers Road east of Lorraine Drive at the existing traffic signal. The raised pedestrian crossing includes pavement markings, signage, and a “speed hump” to provide greater visibility of the crossing area and help slow down traffic. Construction will start on August 12, 2024 and finish by August 30, 2024. Myers Road between Lorraine Drive and Greenbrier Road will be fully closed to through traffic for the duration of the work. Only local access will be permitted. For more information, please visit the Region's website.

  • June 2024 Update

    Share June 2024 Update on Facebook Share June 2024 Update on Twitter Share June 2024 Update on Linkedin Email June 2024 Update link

    Construction of the pedestrian/cycling ramp connection from Myers Road to California Road is planned to proceed in July 2024 until December 2024. The project includes a new concrete ramp with retaining walls, handrails, lighting, and replacing noise walls adjacent to the ramp.

    Construction will start on or about July 8, 2024. The project is expected to be completed by December 2024.

    Myers Road between Gatehouse Road/Lisbon Pines Drive and Branchton Road will be closed to eastbound traffic for the duration of construction. Westbound traffic will be maintained on Myers Road during the construction