Share October update - trail reopening on Facebook
Share October update - trail reopening on Linkedin
Email October update - trail reopening link
We are happy to report that the trail from University Ave East will be open to the public the morning of Saturday October 26th, 2024. The City's contractor has been working hard to be able to reopen the trail off of University Ave East as soon as possible for residents. The contractor may be working adjacent to the trail but will be using limited equipment that should not impact trail users. Please be mindful when using the trail as workers may be present.
Share Construction update - August 20 on Facebook
Share Construction update - August 20 on Linkedin
Email Construction update - August 20 link
Due to higher-than-normal rainfall the weekend of August 17 and 18, the work in Hillside Park has been slightly delayed. The contractor did everything reasonable to protect the site from increased flows in the creek, and has been able to resume work now that creek flows have returned to normal. This delay means that the trail off of Lexington Road will be closed for a few additional days. The contractor is working to open the trail at the end of day Friday, August 30.
Share Summer 2024 project update on Facebook
Share Summer 2024 project update on Linkedin
Email Summer 2024 project update link
The City of Waterloo has scheduled work on Laurel Creek from August 2024 and October 2024. This work requires some of the trails adjacent to the creek to be closed temporarily to allow the contractor safe access to the work site for equipment, materials and deliveries. Please see the detour maps below for detailed closure areas and timelines.
Share Winter 2024 project update on Facebook
Share Winter 2024 project update on Linkedin
Email Winter 2024 project update link
The City of Waterloo has secured a contractor to complete the project's construction. Necessary tree removals will be completed in March 2024 with construction taking place between July and September 2024.
During construction, parts of the trail through the park will need to be closed to pedestrians and cyclists to allow the contractor safe access to the work sites for equipment, materials and deliveries. The work on Forwell Creek will need to have a portion of Hillside Trail closed between Lexington Road and Forwell Creek. The Laurel Creek work will close the part of Hillside Trail between University Avenue and the wastewater treatment plant.
A detailed construction schedule will be posted shortly and will identify when the trail closures will be in place.
Share Summer 2023 project update on Facebook
Share Summer 2023 project update on Linkedin
Email Summer 2023 project update link
In securing bids for this project's construction, the bids all exceeded the allocated budget. As a result, the City has made the decision to cancel the current tender process. Our plan moving forward involves revisiting the 2024 budget to make necessary adjustments. Our goal is to initiate a new tender process in early 2024, with the intention of commencing construction from July/August to September 2024.
Share Notice of Project on Facebook
Share Notice of Project on Linkedin
Email Notice of Project link
The City of Waterloo would like to notify residents of upcoming construction in Hillside Park. Sections of Forwell and Laurel Creeks will be rehabilitated by a contractor procured by the City. The procurement process will start shortly with construction expected to begin in August or early September. During construction, parts of the trail through the park will need to be closed to pedestrians and cyclists to allow the contractor safe access to the work sites for equipment, materials and deliveries. The work on Forwell Creek will need to have a portion of Hillside Trail closed between Lexington Road and Forwell Creek. The Laurel Creek work will close the part of Hillside Trail between University Avenue and the wastewater treatment plant. Details on the trail closures will be provided as soon as they are available.