Construction update - June 17 to June 28
Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
Residents may have noticed the previous schedule did not follow timelines. As noted in the Information Package, the restoration phase doesn’t always go quickly. Waiting for concrete to cure adcoordinating different crews and sub-contractors took longer than expected.
The plan for construction for the next two weeks is:
- Form and pour concrete sidewalk on west side of Hillcrest.
- Form and pour concrete driveway aprons, and restore concrete driveways.
- Place, grade and compact granular base for roadway.
- Pave base asphalt (tentatively scheduled on or about June 26, 2024.)
Exact dates for the work above is difficult to predict, but the work will generally occur in the order shown.
The remaining work, which may or may not get started during the upcoming two-week period, will likely be completed in the following order:
- Asphalt driveways.
- Topsoil/Sod and Interlock driveways and walkways.
- Signage and pavement markings.
- Flushing, cleaning and inspection of new storm and sanitary sewers.
Reminder: Please keep pets (especially cats) inside or on a leash during concrete placement. Concrete will not be replaced for aesthetic reasons such as cat prints in the finish.