Construction update - July 2 to July 12
Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
The schedule for construction the week of July 2, 2024 is tentatively:
- Placement of topsoil.
- Flushing, cleaning and laser profiling of newly installed sewers.
- Line painting and installation of signage.
The schedule for construction the week of July 8, 2024 is tentatively:
- Placement of sod and start of watering.
- Closed-circuit television Inspection of newly installed sewers.
In approximately two weeks the City will walkthrough and inspect the work completed. If any deficiencies are noted, the contractor may return to repair them. The repairs may occur immediately or may occur later in the fall, depending on schedules.
The City does not do surface asphalt until a year following construction to allow time for settling or other deficiencies to appear. The process generally involves one crew arriving to raise the lids of manholes/catch basins and replace the asphalt curb with a concrete curb. Then a separate crew arrives some days later to place the surface layer of asphalt.