Construction Update – April 22 to 26
Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
The current plan for construction over the next week is:
- Monday April 22 – Install storm manholes and sewer at intersection of Hillcrest and Alexandra Ave.
- Following storm installation – resume replacement of sanitary sewer starting midblock and ending just shy of William St.
- Time permitting – Grout fill and abandon existing watermain and begin installation of new watermain, starting at Alexandra and moving towards William St.
Share Construction Update – April 22 to 26 on Facebook
Share Construction Update – April 22 to 26 on Twitter
Share Construction Update – April 22 to 26 on Linkedin
Email Construction Update – April 22 to 26 link