Construction Update 3 – April 29 to May 3

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.

The current plan for construction over the next week is:

  • Start replacing sanitary and water service laterals for each individual house. Lateral pipes will be replaced from the main to the property line.
  • Install storm sewers starting from Alexandra and running south to mid-block.
  • Miscellaneous work until William St W intersection is shutdown starting Tuesday May 7 to complete installation of underground infrastructure (storm, sanitary and water)

The contractor has found Rogers cable wires running shallow through the boulevard on the west side of the street. Theses wires were not located, are unexpectedly shallow and in certain areas hugging infrastructure that is being removed. Some wires have already been accidentally cut by the Contractor and repaired by Rogers. If you have Rogers internet/cable and it stops working, please refer to the instructions in the “Public Information Package for public meeting 2” regarding loss of internet.

Residents frequently complain to the City regarding the wires strung through the trees after construction is finished. Please note that these wires are owned by Rogers and only they are permitted to re-bury them. For more information on this please refer to the following link: https://www.rogers.com/support/internet/cable-burial-process