Phase 2 Construction Update – Anticipated Schedule as of July 6

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.

The following update is the anticipated schedule for upcoming weeks:

  1. Work by concrete sub-contractor
    1. Complete sidewalk
    2. Complete driveway aprons, walkways and other concrete works
  2. Works by asphalt sub-contractor
    1. Asphalt roadway
    2. Asphalt driveway
  3. Works by landscape sub-contractor
    1. Interlock stone driveways and walkways
    2. Place topsoil, grade and place sod

Warning: Residents can walk on concrete after 24 hours, but cannot drive on it for 72 hours.

The restoration of surface works will generally progress in the order noted above. Delays to any step in the process will delay every step that follows. The schedules of the various sub-contractor do not always align which may result in some delays between steps.

Share Phase 2 Construction Update – Anticipated Schedule as of July 6 on Facebook Share Phase 2 Construction Update – Anticipated Schedule as of July 6 on Twitter Share Phase 2 Construction Update – Anticipated Schedule as of July 6 on Linkedin Email Phase 2 Construction Update – Anticipated Schedule as of July 6 link