Contractor Introduction, Parking and Pre-Condition Inspection

The City of Kitchener has awarded Sierra Infrastructure the contract for reconstruction work on Conway Drive and Wayne Drive. Construction is scheduled to start on/or about April 11, 2023 with an anticipated completion on/or about September 6, 2024.

As the City Project Manager, Rob Trussler is a key point of contact; his information has been provided in the contact list below. A Construction Inspector will be on site daily while the contractor is working. Should you have any questions or concerns while the work is in progress the Construction Inspector can be identified by the white hardhat and can be approached at any time. Should you experience an after-hours emergency, please contact the 24-hour Contact Centre at 519-741-2345.

The Contractor will start the project with the setup of their temporary watermain and by completing the pre-condition inspection.

Pre-Condition Inspection of Structures

On heavy construction projects, it is the City of Kitchener’s standard practice to offer to inspect any buildings that might be affected by construction activities before construction starts. If during or after construction residents/tenants experience any concerns with their property, the information from the pre-construction inspection will prove very helpful in quickly and accurately resolving any claims, should they arise.

The pre-condition survey will be conducted by Englobe and if they haven’t already, they will be contacting you within the next few days to arrange for this inspection, which will include inspection of the interior and exterior of each property to document the existing condition prior to construction. In large high-rise apartment buildings, the ground floor area will be inspected, but the individual apartment units above will not be inspected.

We appreciate that some tenants/residents may not want a pre-condition survey of their home and we would like to stress that you are under no obligation to do so. Should this be the case, please advise the representative when they call.

You will likely feel some vibrations during the routine operation of construction equipment; however, studies have shown that these vibrations are much less severe than the vibration level likely to cause structural damage. We do recommend that you remove light, fragile or delicate objects from shelves when construction activity is taking place adjacent to your property.

Should you experience any problems during construction, please contact me immediately and I’ll address or direct your concern to the contractor if needed. If immediate action is needed, such as an issue with your services and City Staff or Representatives are not immediately available, you are welcome to contact the contractor directly.

Should situations arise during or after this construction project, the contact information and telephone numbers are provided below for your convenience.

On Street Parking

During reconstruction, temporary parking permits will be issued to displaced residents to allow on-street parking when needed. The permits will list streets for parking options as you will be permitted to park longer than 3 hours and overnight. Permits are to be displayed on the dash of your vehicle. Ensure that your vehicle is parked in permitted areas only and that you do not interfere with any construction operations.

We communicate with the Bylaw Enforcement team to ensure residents displaced by construction are noted, although illegal parking and/or safety related issues will continue to be enforced. If you require parking enforcement, please contact 519-741-2345. If you have any inquiries, please speak to the site inspector for further direction.

Contacts

City of Kitchener Project Manager

Rob Trussler – 519-741-2200 ext. 7605

Contractor – Sierra Infrastructure

Jacob Runnalls – 519-533-2627

Corporate Contact Centre (24 hour)

519-741-2345

Share Contractor Introduction, Parking and Pre-Condition Inspection on Facebook Share Contractor Introduction, Parking and Pre-Condition Inspection on Twitter Share Contractor Introduction, Parking and Pre-Condition Inspection on Linkedin Email Contractor Introduction, Parking and Pre-Condition Inspection link

The construction is now complete, and the project has entered the maintenance phase. This means we will inspect all aspects of the work done to ensure that it meets our standards. We will also address any deficiencies. Once this phase is complete, we will add a final layer of surface asphalt. This is usually about two years from the start of maintenance. If you have any questions or concerns, please contact the Engineering division at 519-741-2345 or engineering@kitchener.ca


<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>