Construction update 5
Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
The current plan for construction prior to December 25, 2024 is:
- Complete soft armouring by end of end of week (December 20).
- Continue with placement of topsoil behind new retaining walls.
- Install sod (grass) where progress and weather allow. Sod availability limited by weather at this time of year. Some areas slated for sod may need to wait until Spring 2025.
- Hydroseed areas designated to receive native grass seed mix.
The plan for work that may start prior to December 25, 2024, but likely completed in early January is:
- Installation of channel substrate material (riverstone) within the channel once retaining walls are complete.
- Once riverstone substrate installed, complete remaining retaining walls where gaps have been left for access.
- Finish any landscape restoration that is feasible, based on weather conditions.
Please note that the contractor may have crews working on Saturdays AND Sundays. The Contractor’s will not be working from December 25 to January 2 during their winter shutdown.
Some landscape restoration work will need to wait until Spring 2025, such as landscape plantings (i.e. shrubs and trees), restoration of fences and interlocking patios. Please contact the project manager if you have any questions regarding restoration on your property.