Construction update 4
Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.
The current plan for construction over the two-week period from November 27 to December 11, 2024 is:
- Complete construction of the hard armoured (i.e. armour stone) retaining walls, with some areas left unfinished for access.
- Complete work in Clair Creek at east end of site by installing new riverstone base.
- Begin soft armoured retaining walls. Soft armour wall started behind 130 Keats Way Place, working west and turning south towards Keats Way.
- Possibly start installation of riverstone in channel behind residents.
Please note that the contractor may have crews working on Saturdays AND Sundayd moving forward.
Share Construction update 4 on Facebook
Share Construction update 4 on Twitter
Share Construction update 4 on Linkedin
Email Construction update 4 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends