Albert Street Watermain Replacement (Longwood to Weber)
Welcome to the project page for Albert Street (Longwood Dr to Weber St N) Watermain Replacement and Road and Drainage Improvements Project. The reconstruction of Albert Street will include, but is not necessarily limited to, replacement of the watermain, culvert (with headwall) crossing Albert Street (near Weber Street N), one set of catch basins (including leads) draining to Cedar creek, curb and gutter, sidewalk, bike lane separator curbs, asphalt and related infrastructure and coordination with utilities. The City of Waterloo will be tendering the project and overseeing the Consultant from design through construction.
This page will be used for updates and information regarding the project work. Typically, major notices and updates will be posted here as well as included in hard copy notices delivered to residents/owners. Minor updates may be posted on Engage Waterloo only. Subscribe to follow this project and to receive updates as they become available.
Welcome to the project page for Albert Street (Longwood Dr to Weber St N) Watermain Replacement and Road and Drainage Improvements Project. The reconstruction of Albert Street will include, but is not necessarily limited to, replacement of the watermain, culvert (with headwall) crossing Albert Street (near Weber Street N), one set of catch basins (including leads) draining to Cedar creek, curb and gutter, sidewalk, bike lane separator curbs, asphalt and related infrastructure and coordination with utilities. The City of Waterloo will be tendering the project and overseeing the Consultant from design through construction.
This page will be used for updates and information regarding the project work. Typically, major notices and updates will be posted here as well as included in hard copy notices delivered to residents/owners. Minor updates may be posted on Engage Waterloo only. Subscribe to follow this project and to receive updates as they become available.
Please share any questions you may have about this project with our project team.
Your username and question will be published on this site for public viewing. Please note, if you choose to identify yourself with your first and last name in the username field, your name will be available for public viewing. For more information, please refer to our privacy policy.
-
Share Will the City or the City's contractor complete the resurfacing on the last 100M of Albert St where it intersects with Weber St N. The existing stretch of road is in poor condition and was left improperly marked which is causing safety hazards for bike lane users & local pedestrians. on Facebook Share Will the City or the City's contractor complete the resurfacing on the last 100M of Albert St where it intersects with Weber St N. The existing stretch of road is in poor condition and was left improperly marked which is causing safety hazards for bike lane users & local pedestrians. on Twitter Share Will the City or the City's contractor complete the resurfacing on the last 100M of Albert St where it intersects with Weber St N. The existing stretch of road is in poor condition and was left improperly marked which is causing safety hazards for bike lane users & local pedestrians. on Linkedin Email Will the City or the City's contractor complete the resurfacing on the last 100M of Albert St where it intersects with Weber St N. The existing stretch of road is in poor condition and was left improperly marked which is causing safety hazards for bike lane users & local pedestrians. link
Will the City or the City's contractor complete the resurfacing on the last 100M of Albert St where it intersects with Weber St N. The existing stretch of road is in poor condition and was left improperly marked which is causing safety hazards for bike lane users & local pedestrians.
Carter asked over 1 year agoThe section of Albert Street from Longwood to Weber is currently being reviewed and considered in the 2024-2027 budget process. We are aware of the concerns raised here and are actively working on solutions.
-
Share i noticed late last year that the intersection of Albert and Bearinger has had signage installed on all four corners indicating "No right turn on a red light, except for bicycles" I don't understand the logic of not being able to turn right on a red light. Was this part of the original plan or an after thought. What is the reasoning on Facebook Share i noticed late last year that the intersection of Albert and Bearinger has had signage installed on all four corners indicating "No right turn on a red light, except for bicycles" I don't understand the logic of not being able to turn right on a red light. Was this part of the original plan or an after thought. What is the reasoning on Twitter Share i noticed late last year that the intersection of Albert and Bearinger has had signage installed on all four corners indicating "No right turn on a red light, except for bicycles" I don't understand the logic of not being able to turn right on a red light. Was this part of the original plan or an after thought. What is the reasoning on Linkedin Email i noticed late last year that the intersection of Albert and Bearinger has had signage installed on all four corners indicating "No right turn on a red light, except for bicycles" I don't understand the logic of not being able to turn right on a red light. Was this part of the original plan or an after thought. What is the reasoning link
i noticed late last year that the intersection of Albert and Bearinger has had signage installed on all four corners indicating "No right turn on a red light, except for bicycles" I don't understand the logic of not being able to turn right on a red light. Was this part of the original plan or an after thought. What is the reasoning
David Joslin asked almost 2 years agoThere have been a few inquiries about the bike lanes and no right turn on red signs on Albert Street. Many of the cycling projects in the City's Transportation Master Plan were identified to receive separated cycling facilities, including Albert Street. The planning and design of the watermain replacement on Albert Street was an opportunity to address active user needs in the area including the addition of separated cycling lanes, pedestrian islands, new and improved transit stops and improved crossings at a number of intersections. This specific route makes cycling connections to the existing multi-use-paths on Weber Street, the off-road Waterloop multi-use-trail system, as well as the multi-use-paths constructed recently on Phillip Street (which also connects users to LRT stations and the Transit Hub located adjacent the University of Waterloo main campus).
The cycling lanes and their signs have been added in anticipation of increased use as other cycling connections continue to be made. The introduction of No Right Turn on Red signs is consistent with provincial guidelines, and these signs are becoming more widely used around the City and the Region.
-
Share When grt services be resumed from albert longwood on Facebook Share When grt services be resumed from albert longwood on Twitter Share When grt services be resumed from albert longwood on Linkedin Email When grt services be resumed from albert longwood link
When grt services be resumed from albert longwood
Hsnjt asked about 2 years agoRoute 19 has now resumed its normal operations. Thank you for your patience with us, the Region and the GRT as we all worked together to get back to the normal route with the normal stop locations.
-
Share I am a property owner at Albert and Weber, trying to rent my townhouse for students right now (for Jan.1). The rerouted GRT bus #19 is a concern to many applicants. Do you have an idea when it would return to normal please? I see Weber St. there is almost done with asphalt repaving so hoping you will be talking to GRT soon? If you could let me know as soon as possible please! on Facebook Share I am a property owner at Albert and Weber, trying to rent my townhouse for students right now (for Jan.1). The rerouted GRT bus #19 is a concern to many applicants. Do you have an idea when it would return to normal please? I see Weber St. there is almost done with asphalt repaving so hoping you will be talking to GRT soon? If you could let me know as soon as possible please! on Twitter Share I am a property owner at Albert and Weber, trying to rent my townhouse for students right now (for Jan.1). The rerouted GRT bus #19 is a concern to many applicants. Do you have an idea when it would return to normal please? I see Weber St. there is almost done with asphalt repaving so hoping you will be talking to GRT soon? If you could let me know as soon as possible please! on Linkedin Email I am a property owner at Albert and Weber, trying to rent my townhouse for students right now (for Jan.1). The rerouted GRT bus #19 is a concern to many applicants. Do you have an idea when it would return to normal please? I see Weber St. there is almost done with asphalt repaving so hoping you will be talking to GRT soon? If you could let me know as soon as possible please! link
I am a property owner at Albert and Weber, trying to rent my townhouse for students right now (for Jan.1). The rerouted GRT bus #19 is a concern to many applicants. Do you have an idea when it would return to normal please? I see Weber St. there is almost done with asphalt repaving so hoping you will be talking to GRT soon? If you could let me know as soon as possible please!
Norine Lum asked about 2 years agoThank you for your question. Throughout the construction project we have maintained constant communication with GRT. Based on the Albert and Weber schedules, we are expecting to have GRT running on normal routes in the area before the end of November. Currently, Weber (a Region of Waterloo project) is scheduled to reopen by the end of this week, and Albert (our project) will be closing Phillip and Hazel intersections for paving for three days on or near Nov 14-16. Once this work is done, we expect GRT service to resume normal operations.
All of the dates above are subject to change due to weather, unexpected conditions, as well as labour and material availability. Thank you for your patience.
-
Share When are the work suppose to finish , way to disturbing I don’t want apologies but an honest answer thanks on Facebook Share When are the work suppose to finish , way to disturbing I don’t want apologies but an honest answer thanks on Twitter Share When are the work suppose to finish , way to disturbing I don’t want apologies but an honest answer thanks on Linkedin Email When are the work suppose to finish , way to disturbing I don’t want apologies but an honest answer thanks link
When are the work suppose to finish , way to disturbing I don’t want apologies but an honest answer thanks
Alexandre g asked about 2 years agoWeber Street (a Region of Waterloo project) is currently scheduled to be reopened by the end of next week, November 11. Albert Street from Phillip to Columbia is scheduled to be paved the week of November 7. The intersections of Hazel at Albert and Phillip at Albert cannot be closed for paving until Weber Street is reopened, so we tentatively have the paving of these two intersections and the road between them for November 14 to 16, subject to change based on weather and labour availability.
We understand the road closures have been disruptive and a challenge, and that the Weber closure has gone on much longer than the Region expected. These delays have in turn impacted the Albert Street schedule. We are nearing completion of the Albert Street project and need a few more weeks to finish things up. Thank you for your continued patience as we finish this large city project.
-
Share When is Weber opening? It has been longer than the 7 weeks posted on the sign. Columbia is closed, Albert is closed, Weber is closed. The traffic flow at Bearringer/Hazel and Albert is awful. At the very least traffic lights should have been adjusted to account for the extra east/west traffic. on Facebook Share When is Weber opening? It has been longer than the 7 weeks posted on the sign. Columbia is closed, Albert is closed, Weber is closed. The traffic flow at Bearringer/Hazel and Albert is awful. At the very least traffic lights should have been adjusted to account for the extra east/west traffic. on Twitter Share When is Weber opening? It has been longer than the 7 weeks posted on the sign. Columbia is closed, Albert is closed, Weber is closed. The traffic flow at Bearringer/Hazel and Albert is awful. At the very least traffic lights should have been adjusted to account for the extra east/west traffic. on Linkedin Email When is Weber opening? It has been longer than the 7 weeks posted on the sign. Columbia is closed, Albert is closed, Weber is closed. The traffic flow at Bearringer/Hazel and Albert is awful. At the very least traffic lights should have been adjusted to account for the extra east/west traffic. link
When is Weber opening? It has been longer than the 7 weeks posted on the sign. Columbia is closed, Albert is closed, Weber is closed. The traffic flow at Bearringer/Hazel and Albert is awful. At the very least traffic lights should have been adjusted to account for the extra east/west traffic.
JPF asked about 2 years agoWeber Street is a Region of Waterloo project and is currently scheduled to be reopened by the end of next week, November 11. Albert Street from Phillip to Columbia is scheduled to be paved the week of November 7. The intersections of Hazel at Albert and Phillip at Albert cannot be closed for paving until Weber Street is reopened, so we tentatively have the paving of these two intersections and the road between them for November 14 to 16, subject to change based on weather and labour availability.
We understand the road closures have been disruptive and a challenge, and that the Weber closure has gone on much longer than the Region expected. These delays have in turn impacted the Albert Street schedule. We are nearing completion of the Albert Street project and need a few more weeks to finish things up. Thank you for your continued patience as we finish this large city project.
-
Share When will buses return to Albert St? on Facebook Share When will buses return to Albert St? on Twitter Share When will buses return to Albert St? on Linkedin Email When will buses return to Albert St? link
When will buses return to Albert St?
Nori asked about 2 years agoThank you for your question. Weber Street is expected to reopen near the end of October, and Albert Street is expected to reopen in stages through October and November. We are coordinating with Grand River Transit to reinstate regular bus service as soon as road openings make it possible.
-
Share Why is Albert being narrowed to two very narrow lanes when we know that there will be hundreds more cars coming from the new apartment buildings on Quiet Place? on Facebook Share Why is Albert being narrowed to two very narrow lanes when we know that there will be hundreds more cars coming from the new apartment buildings on Quiet Place? on Twitter Share Why is Albert being narrowed to two very narrow lanes when we know that there will be hundreds more cars coming from the new apartment buildings on Quiet Place? on Linkedin Email Why is Albert being narrowed to two very narrow lanes when we know that there will be hundreds more cars coming from the new apartment buildings on Quiet Place? link
Why is Albert being narrowed to two very narrow lanes when we know that there will be hundreds more cars coming from the new apartment buildings on Quiet Place?
Dave U asked over 2 years agoThank you for posting your question. During the initial investigations, it became clear the traffic needs of Albert Street do not and will not necessitate four lanes of vehicle traffic. A 2-lane roadway with appropriate turn lanes can accommodate 20,000+ vehicles per day. A 4 lane roadway considerably more. In 2021, traffic volumes were less than 6,000 per day. To ensure adequate vehicle movement, turn lanes are included in the design at all signalized intersections and other locations where appropriate – this includes and accounts for the planned development at Quiet Place. In addition to the low traffic volumes, traffic speeds were high – upwards of 70km/h. This street was identified as a need for separated cycling per the Transportation Master Plan to connect to existing and other planned cycling infrastructure in the area. The work being completed now will provide for and encourage people to use alternate modes of transportation, such as transit, bicycles and walking, as the area will be much safer and they will be physically separated from the vehicles on the road. We expect total people movement on Albert St will be positively impacted by the new roadway.
-
Share Was it taken into account that a huge apartment complex is going up right here at Quiet Place? The volume of cars will greatly increase, yet the street is being significantly reduced (down to one tight lane in each direction). Has this been factored in? Will there be some other egress for Quiet Place (seems unlikely given the LRT track)? There's a lot that's concerning about these changes (though there's some good too, such as the new crosswalks/islands). on Facebook Share Was it taken into account that a huge apartment complex is going up right here at Quiet Place? The volume of cars will greatly increase, yet the street is being significantly reduced (down to one tight lane in each direction). Has this been factored in? Will there be some other egress for Quiet Place (seems unlikely given the LRT track)? There's a lot that's concerning about these changes (though there's some good too, such as the new crosswalks/islands). on Twitter Share Was it taken into account that a huge apartment complex is going up right here at Quiet Place? The volume of cars will greatly increase, yet the street is being significantly reduced (down to one tight lane in each direction). Has this been factored in? Will there be some other egress for Quiet Place (seems unlikely given the LRT track)? There's a lot that's concerning about these changes (though there's some good too, such as the new crosswalks/islands). on Linkedin Email Was it taken into account that a huge apartment complex is going up right here at Quiet Place? The volume of cars will greatly increase, yet the street is being significantly reduced (down to one tight lane in each direction). Has this been factored in? Will there be some other egress for Quiet Place (seems unlikely given the LRT track)? There's a lot that's concerning about these changes (though there's some good too, such as the new crosswalks/islands). link
Was it taken into account that a huge apartment complex is going up right here at Quiet Place? The volume of cars will greatly increase, yet the street is being significantly reduced (down to one tight lane in each direction). Has this been factored in? Will there be some other egress for Quiet Place (seems unlikely given the LRT track)? There's a lot that's concerning about these changes (though there's some good too, such as the new crosswalks/islands).
Jeff Wilson asked over 2 years agoThank you for posting your question. During the initial investigations, it became clear the traffic needs of Albert Street do not and will not necessitate four lanes of vehicle traffic. A 2-lane roadway with appropriate turn lanes can accommodate 20,000+ vehicles per day. A 4 lane roadway considerably more. In 2021, traffic volumes were less than 6,000 per day. To ensure adequate vehicle movement, turn lanes are included in the design at all signalized intersections and other locations where appropriate – this includes and accounts for the planned development at Quiet Place. In addition to the low traffic volumes, traffic speeds were high – upwards of 70km/h. This street was identified as a need for separated cycling per the Transportation Master Plan to connect to existing and other planned cycling infrastructure in the area. The work being completed now will provide for and encourage people to use alternate modes of transportation, such as transit, bicycles and walking, as the area will be much safer and they will be physically separated from the vehicles on the road. We expect total people movement on Albert St will be positively impacted by the new roadway.
-
Share Since I live in the area, I have to admit I am very disappointed to see how narrow Albert Street is becoming. Can I assume a traffic study has been completed and that there will not be an issue with gridlock now or in the future when planned high-rises are completed in the area and coupled with the recent reductions in lanes of traffic on King Street? The only North/South street with reasonable ability to handle rush hour traffic now seems to be Weber Street, since we all know the 'expressway' at this end of Waterloo is a parking lot during rush hour. on Facebook Share Since I live in the area, I have to admit I am very disappointed to see how narrow Albert Street is becoming. Can I assume a traffic study has been completed and that there will not be an issue with gridlock now or in the future when planned high-rises are completed in the area and coupled with the recent reductions in lanes of traffic on King Street? The only North/South street with reasonable ability to handle rush hour traffic now seems to be Weber Street, since we all know the 'expressway' at this end of Waterloo is a parking lot during rush hour. on Twitter Share Since I live in the area, I have to admit I am very disappointed to see how narrow Albert Street is becoming. Can I assume a traffic study has been completed and that there will not be an issue with gridlock now or in the future when planned high-rises are completed in the area and coupled with the recent reductions in lanes of traffic on King Street? The only North/South street with reasonable ability to handle rush hour traffic now seems to be Weber Street, since we all know the 'expressway' at this end of Waterloo is a parking lot during rush hour. on Linkedin Email Since I live in the area, I have to admit I am very disappointed to see how narrow Albert Street is becoming. Can I assume a traffic study has been completed and that there will not be an issue with gridlock now or in the future when planned high-rises are completed in the area and coupled with the recent reductions in lanes of traffic on King Street? The only North/South street with reasonable ability to handle rush hour traffic now seems to be Weber Street, since we all know the 'expressway' at this end of Waterloo is a parking lot during rush hour. link
Since I live in the area, I have to admit I am very disappointed to see how narrow Albert Street is becoming. Can I assume a traffic study has been completed and that there will not be an issue with gridlock now or in the future when planned high-rises are completed in the area and coupled with the recent reductions in lanes of traffic on King Street? The only North/South street with reasonable ability to handle rush hour traffic now seems to be Weber Street, since we all know the 'expressway' at this end of Waterloo is a parking lot during rush hour.
inawilhelm asked over 2 years agoThank you for posting your question. During the initial investigations, it became clear the traffic needs of Albert Street do not and will not necessitate four lanes of vehicle traffic. A 2-lane roadway with appropriate turn lanes can accommodate 20,000+ vehicles per day. A 4 lane roadway considerably more. In 2021, traffic volumes were less than 6,000 per day. To ensure adequate vehicle movement, turn lanes are included in the design at all signalized intersections and other locations where appropriate – this includes and accounts for the planned development at Quiet Place. In addition to the low traffic volumes, traffic speeds were high – upwards of 70km/h. This street was identified as a need for separated cycling per the Transportation Master Plan to connect to existing and other planned cycling infrastructure in the area. The work being completed now will provide for and encourage people to use alternate modes of transportation, such as transit, bicycles and walking, as the area will be much safer and they will be physically separated from the vehicles on the road. We expect total people movement on Albert St will be positively impacted by the new roadway.
Lifecycle
-
Public Meeting #1
Albert Street Watermain Replacement (Longwood to Weber) is currently at this stageThis public information centre (meeting) will be held June 27, 2024 at Albert McCormick Community Centre at 6 p.m. to share more information about the reconstruction of Albert Street.
-
Tender approval Fall 2024
this is an upcoming stage for Albert Street Watermain Replacement (Longwood to Weber)The award of the construction tender is dependent on Council Approval.
-
Construction begins
this is an upcoming stage for Albert Street Watermain Replacement (Longwood to Weber)Spring 2025.
-
Construction complete
this is an upcoming stage for Albert Street Watermain Replacement (Longwood to Weber)Fall 2025.
Who's Listening
-
Phone 519-886-1550 x78248 Email Mike.Lupsa@waterloo.ca
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends