Westwood Drive: Westmount Road West to Glasgow Street
Share Westwood Drive: Westmount Road West to Glasgow Street on FacebookShare Westwood Drive: Westmount Road West to Glasgow Street on TwitterShare Westwood Drive: Westmount Road West to Glasgow Street on LinkedinEmail Westwood Drive: Westmount Road West to Glasgow Street link
As part of the City of Kitchener’s ongoing efforts to provide consistent and reliable service, staff has scheduled road and sewer improvements in your neighbourhood on the street(s) listed above.
These improvements are scheduled to begin around April 14, 2025 with an estimated completion date on or around November 27, 2026.
The reconstruction is being done to replace the older, deteriorated underground services. The project will be funded through utility user fees and will not result in a direct charge to the homeowner. The following is a brief list of specific improvements being considered:
Upgrade the existing storm sewer, sanitary sewer and water mains, including additional hydrants as required
Replace existing sanitary and water services from the new mains to the property line
Curb and gutter will be installed
Upgrade the asphalt roadway
Replace all driveway ramp entrances in concrete
Wider sidewalks to improve pedestrian safety
Improved bus stop access
How you may be affected
For more information about how this construction may affect you, please read the information package
Once a schedule for construction has been confirmed you will be notified. You will also be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.
Progress and major milestones will be posted on this project page. Subscribe to get project updates by using the Stay Informed 'Subscribe' button.
As part of the City of Kitchener’s ongoing efforts to provide consistent and reliable service, staff has scheduled road and sewer improvements in your neighbourhood on the street(s) listed above.
These improvements are scheduled to begin around April 14, 2025 with an estimated completion date on or around November 27, 2026.
The reconstruction is being done to replace the older, deteriorated underground services. The project will be funded through utility user fees and will not result in a direct charge to the homeowner. The following is a brief list of specific improvements being considered:
Upgrade the existing storm sewer, sanitary sewer and water mains, including additional hydrants as required
Replace existing sanitary and water services from the new mains to the property line
Curb and gutter will be installed
Upgrade the asphalt roadway
Replace all driveway ramp entrances in concrete
Wider sidewalks to improve pedestrian safety
Improved bus stop access
How you may be affected
For more information about how this construction may affect you, please read the information package
Once a schedule for construction has been confirmed you will be notified. You will also be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.
Progress and major milestones will be posted on this project page. Subscribe to get project updates by using the Stay Informed 'Subscribe' button.
This survey will ask you about things we may need to consider when planning this road reconstruction. It will also ask you whether you are interested in a storm drain connection.
We appreciate your cooperation. A city staff member may contact you if we need more information about your comments.
If you have any questions, contact Steve Allen, Engineering Manager, at steve.allen@kitchener.ca or 519-741-2200 x7584
This questionnaire is open until June 28, 2024
Share Resident/Owner Questionnaire on FacebookShare Resident/Owner Questionnaire on TwitterShare Resident/Owner Questionnaire on LinkedinEmail Resident/Owner Questionnaire link
Page last updated: 14 Nov 2024, 02:16 PM
Follow Project
Stay informed
Subscribe for project updates
Lifecycle
Project Announced
Westwood Drive: Westmount Road West to Glasgow Street has finished this stage
Please review this page for information about this upcoming road reconstruction project
Questionnaire Open
Westwood Drive: Westmount Road West to Glasgow Street is currently at this stage
Please answer our resident/owner questionnaire, which helps us design the reconstruction project while taking your circumstances into consideration
Review and Preparation
this is an upcoming stage for Westwood Drive: Westmount Road West to Glasgow Street
We are reviewing the questionnaire results and preparing for the reconstruction of this road
Under Construction
this is an upcoming stage for Westwood Drive: Westmount Road West to Glasgow Street
Construction is now underway on this street
Final Inspection
this is an upcoming stage for Westwood Drive: Westmount Road West to Glasgow Street
We are doing a final review and inspection
Project Complete
this is an upcoming stage for Westwood Drive: Westmount Road West to Glasgow Street
Road reconstructions help Kitchener adapt to climate change
Replacing outdated stormwater pipes and adding green infrastructure during road construction makes Kitchener more resilient to future flooding caused by climate change. This road reconstruction project is funded in part by the Government of Canada. For more information about the City of Kitchener's partnership with the Government of Canada through the Disaster Mitigation and Adaptation Fund, visit kitchener.ca/Stormwater
Soak up rain and reduce runoff
Kitchener has partnered with Reep Green Solutions to help you make changes to beautify your yard and reduce runoff. To learn more and see if you qualify for a free, on-site consultation with a landscape designer, visit Reep's Rain Smart Neighbourhoods.