Project overview
Following the Kitchener City Council approval of the Strasburg Road extension, and Environmental Assessment work done by the City of Kitchener, we’ve reviewed what will become the intersection of Strasburg Road and New Dundee Road to look at ways to ensure this future intersection will consider pedestrian, cyclist, and driver safety, while also minimizing traffic delays. At this time, a roundabout is proposed.
Engagement
We are reviewing the feedback we have received from the survey, the study’s technical findings, industry best practices, and staff expertise to develop a preferred option. We’ll share that option with Regional Council when we take a recommendation forward this June.
Questions?
Please email Jeff Nyenhuis, P.Eng, Engineer at jnyenhuis@regionofwaterloo.ca if you have specific concerns or questions about the project, or need to access the survey in another format.
Key Dates
26 February 2024
Survey and Comments close
28 June 2024
Planning and Works Committee Meeting - Project Approval
Lifecycle
-
Timeline item 1 - complete
Project Open for Public Input until February 26, 2024.
This consultation is Open for contributions.
-
Timeline item 2 - complete
Review comments (March 2024)
Contributions to this consultation are closed for evaluation and review. The project team will report back on key outcomes.
-
Timeline item 3 - complete
Report to Regional Planning and Works Committee for Approval (late spring/ summer, 2024)
-
Timeline item 4 - active
Detailed Design (2024/ 2025)
-
Timeline item 5 - incomplete
Utility Relocations (Spring 2026)
-
Timeline item 6 - incomplete
Tender for Construction (March 2026)
-
Timeline item 7 - incomplete
Construction Start (May 2026)
-
Timeline item 8 - incomplete
Construction Completion (Fall 2026)