February 04 → March 17 2021
Public consultation open
The public is invited to complete the surveys or contact the project team to provide input during this six week period.
April 30 2021
Target for Region response to questions
The project team will target this date to provide responses to all questions received.
June 2021
Final report to Council for approval
Some time in the Spring of 2021 the final report will go to the Planning and Works Committee of Council for approval.
January 01 2022
New Sewer Use Bylaw in effect