Langford Place and Quickfall Drive reconstruction
Welcome to the project page for the planned reconstruction of Quickfall Drive (from Mayfield to the end of Cul-de-Sac) and Langford Place (from Mayfield to the end of Cul-de-Sac). The City intends to reconstruct these roads to replace the aged watermain, sewers and road structure (i.e. sidewalk, curbs and asphalt). This will also include the replacement of water and sanitary service laterals up to the common property line. As per the approved Transportation Master Plan, Langford Place is scheduled to receive new sidewalk on at least one side of the street as part of the road reconstruction.
This page will be used to for updates and information regarding the project work. Typically, major notices and updates will be posted here as well as included in hard copy notices delivered to residents/owners. Minor updates may be posted on Engage Waterloo only. Subscribe to follow this project and to receive updates as they become available.
Welcome to the project page for the planned reconstruction of Quickfall Drive (from Mayfield to the end of Cul-de-Sac) and Langford Place (from Mayfield to the end of Cul-de-Sac). The City intends to reconstruct these roads to replace the aged watermain, sewers and road structure (i.e. sidewalk, curbs and asphalt). This will also include the replacement of water and sanitary service laterals up to the common property line. As per the approved Transportation Master Plan, Langford Place is scheduled to receive new sidewalk on at least one side of the street as part of the road reconstruction.
This page will be used to for updates and information regarding the project work. Typically, major notices and updates will be posted here as well as included in hard copy notices delivered to residents/owners. Minor updates may be posted on Engage Waterloo only. Subscribe to follow this project and to receive updates as they become available.
-
Construction update - May 27, 2024
Share Construction update - May 27, 2024 on Facebook Share Construction update - May 27, 2024 on Twitter Share Construction update - May 27, 2024 on Linkedin Email Construction update - May 27, 2024 linkThe City will start setting up a temporary watermain on Langford Place starting May 31, 2024
-
Public information session
Share Public information session on Facebook Share Public information session on Twitter Share Public information session on Linkedin Email Public information session linkThe City is proceeding with an in-person Public Information Centre (PIC #2) meeting and has prepared an information package detailing general project information and frequently asked questions. Documents to be presented at the public meeting are posted on this page in the key documents section.
1. Plan drawings of Quickfall Dr./Langford PL. and a proposed road cross-section for each.
2. Resident information package.
More information about the reconstruction of Quickfall Drive and Langford Place will be shared at the upcoming public meeting.
Date: Tuesday, April 2, 2024
Time: Drop-in anytime between 6 and 8 p.m.
Place: Moses Springer Community Centre, 150 Lincoln Rd, Waterloo
We appreciate your time, interest and cooperation in this project. Please contact a member of the project team listed on this page with any further questions.
-
Public information session
Share Public information session on Facebook Share Public information session on Twitter Share Public information session on Linkedin Email Public information session linkThe City is proceeding with an in-person Public Information Centre (PIC) meeting and has prepared an information package detailing general project information and frequently asked questions. Documents that would typically be presented at the PIC are posted on this project page below. *This is in addition to the material in the information package.
1. Plan drawings of Quickfall Dr./Langford PL. and a proposed roach cross section for each.
2. Description of the proposed works.
3. General construction information.
4. Comment Sheet – part of the information package, we would appreciate receiving comments by November 3, 2023.
More information about the reconstruction of Quickfall Drive & Langford Place will be shared at the upcoming Public Information Centre.
Date: Tuesday October 24th, 2023
Time: Drop-in anytime between 6 and 8 p.m.
Place: Moses Springer Community Centre, 150 Lincoln Rd, Waterloo
We appreciate your time, interest and cooperation in this project. Please contact a member of the project team listed on this page with any further questions.
-
Notice of Reconstruction
Share Notice of Reconstruction on Facebook Share Notice of Reconstruction on Twitter Share Notice of Reconstruction on Linkedin Email Notice of Reconstruction linkThe City of Waterloo has approved the reconstruction of Quickfall Drive (from Mayfield to the end of Cul-de-Sac) and Langford Place (from Mayfield to the end of Cul-de-Sac), with construction scheduled to start in the Spring of 2024. The City has selected Arcadis-IBI Group to provide design and contract administration services for the reconstruction project. The map below shows the approximate limits of reconstruction.
As part of the reconstruction, all underground municipal infrastructure will be replaced, including sanitary sewer, storm sewer, watermain and sanitary and water services up to the common property line. Surface works will include new concrete curb and gutter, new sidewalks and a new pavement structure. Areas disturbed by construction, such as walkways, driveways and grassed areas, will be restored to City standards. Please note that the City standard for boulevards within the public right-of-way is topsoil and sod. Private landscaping by residents within the public portion of the boulevard will not be replaced by the City.
Arcadis-IBI Group will be in the area during the period of June 19 to July 1, 2023 to complete a topographic survey for the project. The survey will include the frontage of your property as well as the street. The purpose of this survey is to obtain surface elevation data and locate existing features (trees, gardens, steps, walkways, retaining walls, etc.) for preliminary study and engineering design. The surveyors should not interfere with your regular activities and will identify themselves if you have questions.
Additionally, a separate consultant will complete a geotechnical soils investigation in accordance with provincial regulations. This work will likely only take one to two days and will generally only block small sections of roadway and boulevard. The work shouldn’t present a major inconvenience to mobility. However, the equipment used can make short, high-pitched bursts of noise which residents should be prepared for.
The City will provide various notices and updates prior to and during construction. Prior to construction residents will be invited to two in-person Public Information Centre’s (PIC’s). The first PIC will provide information on the proposed design. The second PIC will provide more information on what to expect during construction and provide an opportunity to meet the contractor. As the project progresses the City will be creating a project webpage on Engage Waterloo where relevant project information will be posted.
Where possible the City will make efforts to minimize the amount of disruption to your day-to-day activities; however, major reconstruction projects such as this will inevitably result in some disruptions. Please note the following important information at this stage:
Notify the City’s Project Manager if you have any mobility challenges
During construction, driveway access is generally unavailable during working hours (7am to 7pm). Sidewalks will be maintained to the extent feasible when driveway access is not available. However, there will be times when even sidewalk access is impacted. Knowing any existing challenges in advance will help plan for specific needs.
Hold off replacing driveways or walkways
Construction will result in the ends of driveways and walkways being removed and patched at the end of construction. Waiting to replace driveways and walkways until after construction will avoid the need to cut into new pavement.
Follow Project
Project Timeline
-
Summer 2023
Langford Place and Quickfall Drive reconstruction has finished this stageTopographic surveying, geotechnical investigation and detailed design.
-
Fall 2023
Langford Place and Quickfall Drive reconstruction has finished this stageDesign stage Public Information Centre (in-person)
-
Winter 2023/24
Langford Place and Quickfall Drive reconstruction has finished this stageComplete detailed design. Procure contractor to complete construction
-
March 2024
Langford Place and Quickfall Drive reconstruction has finished this stagePre-construction Public Information Centre (in-person)
-
May 2024
Langford Place and Quickfall Drive reconstruction is currently at this stageTemporary watermain set up begins May 31
-
Fall 2024
this is an upcoming stage for Langford Place and Quickfall Drive reconstructionComplete construction
Project library
- Langford_Quickfall_Resident_InfoPackage_PIC2.pdf (1.2 MB) (pdf)
- Langford_PIC2_Display_Board.pdf (3.37 MB) (pdf)
- Quickfall_PIC2_Display_Board.pdf (2.49 MB) (pdf)
- Langford_PIC_Display_Board.pdf (3.43 MB) (pdf)
- Langford_Quickfall_PIC_Info_Package_Final.pdf (1.3 MB) (pdf)
- Quickfall_PIC_Display_Board.pdf (2.52 MB) (pdf)
Project Team
-
Email mike.lupsa@waterloo.ca -
MM
Phone 519-585-2255 x63207 Email michael.mcgann@arcadis.com