November 28 → December 19 2022

Online public consultation

November 28 2022

Notice of Commencement of project

April 04 2023

Recommendation to Planning and Works Committee (deferred from March 7)

The project team will take a report to Planning and Works Committee recommending the permanent closure of the two ramps at the Lancaster Street and Highway 85 Interchange. This will allow for an AAA cycling facility along with sidewalks on the Lancaster Street Bridge over Highway 85, reduce collisions, and improve overall operations on Highway 85 and in the area.

You can view the staff report, the appendices, and register to delegate at the March 7 Planning and Works Committee meeting. The meeting starts at 11:30 a.m.

May 2023 → September 2024

Design Ramp Solution and Construction (By MTO)