Franklin Street South: Kingsway Drive to Wilson Avenue

Share Franklin Street South: Kingsway Drive to Wilson Avenue on Facebook Share Franklin Street South: Kingsway Drive to Wilson Avenue on Twitter Share Franklin Street South: Kingsway Drive to Wilson Avenue on Linkedin Email Franklin Street South: Kingsway Drive to Wilson Avenue link

The construction is now complete, and the project has entered the maintenance phase. This means we will inspect all aspects of the work done to ensure that it meets our standards. We will also address any deficiencies. Once this phase is complete, we will add a final layer of surface asphalt. This is usually about two years from the start of maintenance. If you have any questions or concerns, please contact us at 519-741-2345 or engineering@kitchener.ca 


Map of project limits


As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff has scheduled road and sewer improvements in your neighbourhood.

These improvements are scheduled to begin, on or about, April 15, 2022, with an estimated completion date on or about November 15, 2023. You will be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.

The specific improvements scheduled for this street are:

  • Upgrade the existing storm sewer, sanitary sewer and water mains.
  • Replace existing sanitary and water services from the new mains to the property line.
  • Curb and gutter, and sidewalks will be installed.
  • Upgrade the asphalt roadway.
  • Replace all driveway ramp entrances in concrete.
  • Addition of on-road bike lanes and shared use roadway markings.

Please read the Information Package for more details about how this construction may affect you.

All residents are also invited to review the Project Info Boards for more information.

Progress and major milestones will be posted on this project page. Subscribe to get project updates by using the Stay Informed 'Subscribe' button.

Road reconstructions help Kitchener adapt to climate change

Replacing outdated stormwater pipes and adding green infrastructure during road construction makes Kitchener more resilient to future flooding caused by climate change. This road reconstruction project is funded in part by the Government of Canada. For more information about the City of Kitchener's partnership with the Government of Canada through the Disaster Mitigation and Adaptation Fund, visit kitchener.ca/Stormwater.

Soak up rain and reduce runoff

Kitchener has partnered with Reep Green Solutions to help you make changes to beautify your yard and reduce runoff. To learn more and see if you qualify for a free, on-site consultation with a landscape designer, visit Reep's Rain Smart Neighbourhoods.


As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff has scheduled road and sewer improvements in your neighbourhood.

These improvements are scheduled to begin, on or about, April 15, 2022, with an estimated completion date on or about November 15, 2023. You will be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.

The specific improvements scheduled for this street are:

  • Upgrade the existing storm sewer, sanitary sewer and water mains.
  • Replace existing sanitary and water services from the new mains to the property line.
  • Curb and gutter, and sidewalks will be installed.
  • Upgrade the asphalt roadway.
  • Replace all driveway ramp entrances in concrete.
  • Addition of on-road bike lanes and shared use roadway markings.

Please read the Information Package for more details about how this construction may affect you.

All residents are also invited to review the Project Info Boards for more information.

Progress and major milestones will be posted on this project page. Subscribe to get project updates by using the Stay Informed 'Subscribe' button.

Road reconstructions help Kitchener adapt to climate change

Replacing outdated stormwater pipes and adding green infrastructure during road construction makes Kitchener more resilient to future flooding caused by climate change. This road reconstruction project is funded in part by the Government of Canada. For more information about the City of Kitchener's partnership with the Government of Canada through the Disaster Mitigation and Adaptation Fund, visit kitchener.ca/Stormwater.

Soak up rain and reduce runoff

Kitchener has partnered with Reep Green Solutions to help you make changes to beautify your yard and reduce runoff. To learn more and see if you qualify for a free, on-site consultation with a landscape designer, visit Reep's Rain Smart Neighbourhoods.

The construction is now complete, and the project has entered the maintenance phase. This means we will inspect all aspects of the work done to ensure that it meets our standards. We will also address any deficiencies. Once this phase is complete, we will add a final layer of surface asphalt. This is usually about two years from the start of maintenance. If you have any questions or concerns, please contact us at 519-741-2345 or engineering@kitchener.ca 


  • Project Info

    Share Project Info on Facebook Share Project Info on Twitter Share Project Info on Linkedin Email Project Info link

    As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff has scheduled road and sewer improvements in your neighbourhood on the street(s) listed above.

    These improvements are scheduled to begin, on or about, April 15, 2022, with an estimated completion date on or about November 15, 2023. You will be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.

    The specific improvements scheduled for this street are:

    Upgrade the existing storm sewer, sanitary sewer and water mains.

    • Replace existing sanitary and water services from the new mains to the property line.
    • Curb and gutter, and sidewalks will be installed.
    • Upgrade the asphalt roadway.
    • Replace all driveway ramp entrances in concrete.
    • Addition of on-road bike lanes and shared use roadway markings.

    These improvements are being done to upgrade the existing, deteriorated underground services and above-ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.

    In order to carry out these improvements, it will be necessary to close this street to through traffic. Prior to any road closure, signs will be posted on the approaching streets advising motorists of the date and the duration of the closure.

    Pedestrian access will be maintained to all properties at all times and vehicular access to all properties within the construction area will be maintained for as long as possible. On-street parking permits, which will allow parking on adjacent side streets, will be hand-delivered to affected homes before vehicular access is cut off.

    Before construction starts, a survey of the existing homes and businesses will be undertaken to determine the condition of the buildings in the construction area. The selected consulting firm will contact you directly to arrange for a voluntary inspection of the exterior and interior of your building. This inspection is done to protect the property owner.