Burn Place / Montrose Avenue / Metzloff Drive / Carlton Street

Share Burn Place / Montrose Avenue / Metzloff Drive / Carlton Street on Facebook Share Burn Place / Montrose Avenue / Metzloff Drive / Carlton Street on Twitter Share Burn Place / Montrose Avenue / Metzloff Drive / Carlton Street on Linkedin Email Burn Place / Montrose Avenue / Metzloff Drive / Carlton Street link
Map of project limits

As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff has scheduled road and sewer improvements in your neighbourhood.

These improvements are scheduled to begin, spring of 2025, with an estimated completion date of fall 2025.

The following is a brief list of the improvements being considered:

    • Upgrade the existing storm sewer, sanitary sewer and water mains, including additional hydrants as required
    • Replace existing sanitary and water services from the new mains to the property line
    • Curb and gutter, and sidewalks will be installed
    • Upgrade the asphalt roadway
    • Replace all driveway ramp entrances in concrete
    • Install and/or replace retaining walls

These improvements are being done to upgrade the existing, deteriorated underground services and above-ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.

As more information becomes available, we will post it to this page. Subscribe to get email notification of project updates by using the Stay Informed 'Subscribe' button above.

As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff has scheduled road and sewer improvements in your neighbourhood.

These improvements are scheduled to begin, spring of 2025, with an estimated completion date of fall 2025.

The following is a brief list of the improvements being considered:

    • Upgrade the existing storm sewer, sanitary sewer and water mains, including additional hydrants as required
    • Replace existing sanitary and water services from the new mains to the property line
    • Curb and gutter, and sidewalks will be installed
    • Upgrade the asphalt roadway
    • Replace all driveway ramp entrances in concrete
    • Install and/or replace retaining walls

These improvements are being done to upgrade the existing, deteriorated underground services and above-ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.

As more information becomes available, we will post it to this page. Subscribe to get email notification of project updates by using the Stay Informed 'Subscribe' button above.

  • Questionnaire now open until Sept. 16

    Share Questionnaire now open until Sept. 16 on Facebook Share Questionnaire now open until Sept. 16 on Twitter Share Questionnaire now open until Sept. 16 on Linkedin Email Questionnaire now open until Sept. 16 link

    To help us address any specific issues or considerations, we ask that you please complete the Resident/Owner Questionnaire. Help us take your needs into consideration when planning the road reconstruction. Help us take your needs into consideration when planning the road reconstruction. We would like to hear from you about:

    • Any issues you had in the past with sewer backups, flooding, or water pressure
    • What we might need to know about you before we begin construction
    • If you have any plans to redevelop your property (example: severance, additional units)
    • Your interest in having a private storm drain connection installed


    Please take a few minutes to answer our Resident/Owner Questionnaire.

    The questionnaire closes Sept. 16, 2024. If you have any questions, reach out to the project manager David Phan at david.phan@kitchener.ca

  • Surveyors in the area

    Share Surveyors in the area on Facebook Share Surveyors in the area on Twitter Share Surveyors in the area on Linkedin Email Surveyors in the area link

    During the next few weeks, you may observe surveyors undertaking a detailed field survey in your neighborhood. The survey is being completed in preparation for the reconstruction of the street(s) listed above.

    In order to gather the required details, the survey will include the frontage of your property as well as the street. The purpose of this survey is to locate all existing features (trees, gardens, steps, and walkways, etc.) on the plans for preliminary study and final design.

    The surveyors should not interfere with your regular activities but will identify themselves if you have any questions.

    If you have any questions and/or concerns about this project, please feel free to contact the Manager, Engineering Design and Approvals, Steve Allen, by email at steve.allen@kitchener.ca