Second Avenue: Kingsway Drive to Connaught Street

Share Second Avenue: Kingsway Drive to Connaught Street on Facebook Share Second Avenue: Kingsway Drive to Connaught Street on Twitter Share Second Avenue: Kingsway Drive to Connaught Street on Linkedin Email Second Avenue: Kingsway Drive to Connaught Street link

The construction is now complete, and the project has entered the maintenance phase. This means we will inspect all aspects of the work done to ensure that it meets our standards. We will also address any deficiencies. Once this phase is complete, we will add a final layer of surface asphalt. This is usually about two years from the start of maintenance. If you have any questions or concerns, please contact us at 519-741-2345 or engineering@kitchener.ca


Map of project limits


As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff has scheduled road and sewer improvements in your neighbourhood.

These improvements are tentatively scheduled to begin, on or about, April 3, 2023, with an estimated completion date on or about September 15, 2023 . Once a schedule for the construction has been confirmed you will be notified. You will also be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.

The specific improvements scheduled for this street are:

  • Upgrade the existing storm sewer, sanitary sewer and water mains.
  • Replace existing sanitary and water services from the new mains to the property line.
  • Curb and gutter, and sidewalks will be installed.
  • Upgrade the asphalt roadway.
  • Replace all driveway ramp entrances in concrete.

The City is proposing some elements of the “Complete Streets” approach including a narrower roadway and a wider sidewalk on the east side of the street. The roadway asphalt width will be reduced from 10.0m to 7.0m. Parking will be allowed as it is currently allowed. The width of the sidewalk on the east side of the street will be increased from the existing width of 1.5m to 1.8m.

Please read the Information Package for more details about how this construction may affect you.

All residents are also invited to review the Project Information Boards for more information.

Progress and major milestones will be posted on this project page. Subscribe to get email notification of project updates by using the Stay Informed 'Subscribe' button.

Road reconstructions help Kitchener adapt to climate change

Replacing outdated stormwater pipes and adding green infrastructure during road construction makes Kitchener more resilient to future flooding caused by climate change. This road reconstruction project is funded in part by the Government of Canada. For more information about the City of Kitchener's partnership with the Government of Canada through the Disaster Mitigation and Adaptation Fund, visit kitchener.ca/Stormwater.

Soak up rain and reduce runoff

Kitchener has partnered with Reep Green Solutions to help you make changes to beautify your yard and reduce runoff. To learn more and see if you qualify for a free, on-site consultation with a landscape designer, visit Reep's Rain Smart Neighbourhoods.


As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff has scheduled road and sewer improvements in your neighbourhood.

These improvements are tentatively scheduled to begin, on or about, April 3, 2023, with an estimated completion date on or about September 15, 2023 . Once a schedule for the construction has been confirmed you will be notified. You will also be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.

The specific improvements scheduled for this street are:

  • Upgrade the existing storm sewer, sanitary sewer and water mains.
  • Replace existing sanitary and water services from the new mains to the property line.
  • Curb and gutter, and sidewalks will be installed.
  • Upgrade the asphalt roadway.
  • Replace all driveway ramp entrances in concrete.

The City is proposing some elements of the “Complete Streets” approach including a narrower roadway and a wider sidewalk on the east side of the street. The roadway asphalt width will be reduced from 10.0m to 7.0m. Parking will be allowed as it is currently allowed. The width of the sidewalk on the east side of the street will be increased from the existing width of 1.5m to 1.8m.

Please read the Information Package for more details about how this construction may affect you.

All residents are also invited to review the Project Information Boards for more information.

Progress and major milestones will be posted on this project page. Subscribe to get email notification of project updates by using the Stay Informed 'Subscribe' button.

Road reconstructions help Kitchener adapt to climate change

Replacing outdated stormwater pipes and adding green infrastructure during road construction makes Kitchener more resilient to future flooding caused by climate change. This road reconstruction project is funded in part by the Government of Canada. For more information about the City of Kitchener's partnership with the Government of Canada through the Disaster Mitigation and Adaptation Fund, visit kitchener.ca/Stormwater.

Soak up rain and reduce runoff

Kitchener has partnered with Reep Green Solutions to help you make changes to beautify your yard and reduce runoff. To learn more and see if you qualify for a free, on-site consultation with a landscape designer, visit Reep's Rain Smart Neighbourhoods.

The construction is now complete, and the project has entered the maintenance phase. This means we will inspect all aspects of the work done to ensure that it meets our standards. We will also address any deficiencies. Once this phase is complete, we will add a final layer of surface asphalt. This is usually about two years from the start of maintenance. If you have any questions or concerns, please contact us at 519-741-2345 or engineering@kitchener.ca


  • Stage Two Sod End of Warranty Letter

    Share Stage Two Sod End of Warranty Letter on Facebook Share Stage Two Sod End of Warranty Letter on Twitter Share Stage Two Sod End of Warranty Letter on Linkedin Email Stage Two Sod End of Warranty Letter link

    As a follow-up to the letter dated August 28, 2023, please be advised the City’s hired contractor has met their contractual obligations as it relates to the care and rectification of the newly sodded areas with the project limits noted above. With the contractor now excused from the watering and maintenance of the newly sodded areas, it is now the property owner’s responsibility to continue the watering, maintenance and care of these newly sodded areas, as required.

    After construction, depression settlement may occur, meaning the soil over the area that was dug up had settled. Should depression occur, rectification of the depression will happen during the project two-year maintenance period.

    Please note new sod can may take up to two years to fully root and establish itself. The weather sun exposure and such can impact the establishment and health of young sod. We encourage property owners to continue periodic watering, care and maintenance of the sod going forward.

    If you have any questions concerning this matter, please do not hesitate to contact the city’s Project Manager by phone at 519-741-2200 ext. 7132 or email at licinio.costa@kitchener.ca

  • Stage Two Sod Start of Warranty Letter

    Share Stage Two Sod Start of Warranty Letter on Facebook Share Stage Two Sod Start of Warranty Letter on Twitter Share Stage Two Sod Start of Warranty Letter on Linkedin Email Stage Two Sod Start of Warranty Letter link

    As part of the completion of the reconstruction of Second Avenue, the city’s contractor has replaced the topsoil and sod on or adjacent to your property.

    The contractor will now be required to provide ongoing maintenance, including watering of the sodded areas until Friday, October 27, 2023. After the 60 days, you will be notified by letter that the sod has been accepted, that it will no longer be subject to a warranty, and that ongoing care and maintenance will become the responsibility of the property owners.

    In an effort to ensure the newly placed sod is given the best chance to root and survive the contractor will be subject to several requirements that will include:

    • Daily watering for the first 7 days after the sod is placed.
    • Ongoing watering during the first 60 days as needed: and
    • Fertilizing with a granulated fertilizer and aeration

    The city will inspect the condition of the newly sodded area at the end of 60 days. The contractor will be required to replace any deteriorated sod noted at the time of inspection. After this inspection and the replacement of any deteriorated sod, the care and maintenance of the sod will become the homeowner’s responsibility.

    After construction, depression settlement may occur, meaning the soil over the area that was dug up had settled. Should depression occur, rectification of the depression will occur during the project two-year maintenance period.

    Please note, new sod may take up to two years to fully root and establish. The weather, sun exposure and such can affect the establishment and health of young sod. We encourage property owners to continue periodic watering (adhering to the Region of Waterloo water use by-law) and care and maintenance after the end of the sod warranty.

    If you have any questions concerning this matter, please do not hesitate to contact the city’s Project Manager at phone number 519-741-2200 ext. 7132 or email at licinio.costa@kitchener.ca.

    If you would like to receive updates for this project as they become available, please subscribe and you will be added to the email list for updates on this project.

  • Stage One Sod End of Warranty Letter

    Share Stage One Sod End of Warranty Letter on Facebook Share Stage One Sod End of Warranty Letter on Twitter Share Stage One Sod End of Warranty Letter on Linkedin Email Stage One Sod End of Warranty Letter link

    As a follow-up to the letter dated June 26, 2023, please be advised the City’s hired contractor has met their contractual obligations as it relates to the care and rectification of the newly sodded areas with the project limits noted above. With the contractor now excused from the watering and maintenance of the newly sodded areas, it is now the property owner’s responsibility to continue the watering, maintenance and care of these newly sodded areas, as required.

    After construction, depression settlement may occur, meaning the soil over the area that was dug up had settled. Should depression occur, rectification of the depression will happen during the project two-year maintenance period.

    Please note new sod can may take up to two years to fully root and establish itself. The weather sun exposure and such can impact the establishment and health of young sod. We encourage property owners to continue periodic watering, care and maintenance of the sod going forward.

    If you would like to receive updates for this project as they become available, please subscribe and you will be added to the email list for updates on this project. Add your email to the Stay Informed box, then click 'Subscribe'.

    If you have any questions concerning this matter, please do not hesitate to contact the city’s Project Manager by phone at 519-741-2200 ext. 7132 or email at licinio.costa@kitchener.ca.

  • Second Avenue - Driveway Access Concrete Works

    Share Second Avenue - Driveway Access Concrete Works on Facebook Share Second Avenue - Driveway Access Concrete Works on Twitter Share Second Avenue - Driveway Access Concrete Works on Linkedin Email Second Avenue - Driveway Access Concrete Works link

    Please be advised that on July 31, 2023, crews have begun working on string line setup for upcoming installation of concrete curb and gutter to follow on Stage 2 of Second Avenue.

    Driveway Access during Concrete Work

    The contractor estimates that driveway access will be lost for about 3-5 weeks while concrete curb and gutter, concrete sidewalk, concrete driveway ramps and asphalt road paving is planned to occur. The duration of lost driveway access is due to several factors including:

    • time required for crews to complete their work,
    • time required for concrete to properly cure to reach its proper strength,
    • subcontractor’s schedule,
    • and other unforeseen factors such as weather.


    Crews will work diligently to complete this work in a timely manner. Wood planks/bridges may be constructed at various points along the site, by the contractor, over the newly poured concrete sidewalks to provide pedestrian access to properties.

    On Street Parking

    During reconstruction, temporary parking permits have been issued to displaced residents to allow on-street parking when needed. The permits list streets for parking options as you will be permitted to park longer than 3 hours and overnight. Permits are to be displayed on the dash of your vehicle. Ensure that your vehicle is parked in permitted areas only and that you do not interfere with any construction operations. We communicate with the Bylaw Enforcement team to ensure residents displaced by construction are noted, although illegal parking and/or safety related issues will continue to be enforced. If you require parking enforcement, please contact 519-741-2345. If you have any inquiries or require additional permits, please speak to the site inspector for further direction or contact me, the construction project manager, directly.

    Accessibility Requirements

    If you have not yet reached out to me, please let me know of any accessibility requirements, and we will work together with the contractor to arrange suitable accommodations. This could include (but not limited to) accessibility parking needs, moving in or out of your residence, special deliveries, etc.

    Curbside Waste Collection

    For curbside waste collection, please write your address on all your containers and have out to curbside by 6 a.m. on your collection day. The contractor is responsible to ensure pickup of your waste items and return your containers within a reasonable amount of time after collection occurs.

    We’re happy to meet with you or discuss by phone, any concerns, questions or feedback that you may have.

    Please do not hesitate to contact me, the City’s Project Manager by phone at 519-741-2200 ext. 7132 or by email at licinio.costa@kitchener.ca.

    If you would like to receive updates for this project as they become available, please subscribe and you will be added to the email list for updates on this project. Add your email to the Stay Informed box then click 'Subscribe'.

    Project Team Contact Information

    City of Kitchener Project Manager

    Licinio Costa – 519-741-2200 ext. 7132

    Consultant Project Manager – Aecom

    Steve Collie – 519-650-8665

    Consultant Construction Inspector – Aecom

    Vincent Bruno – Vincent.bruno@aecom.com

    Contractor – J. Weber Contracting

    Murray Childerhose – 519-648-3302

    Corporate Contact Centre (24 hour)

    519-741-2345

    We appreciate your patience and understanding during this project.

    Sincerely,

    Licinio Costa C.E.T.

    Construction Project Manager | Engineering Services | City of Kitchener

  • Sod Start of Warranty Stage One

    Share Sod Start of Warranty Stage One on Facebook Share Sod Start of Warranty Stage One on Twitter Share Sod Start of Warranty Stage One on Linkedin Email Sod Start of Warranty Stage One link

    As part of the completion of the reconstruction of Second Avenue, the city’s contractor has replaced the topsoil and sod on or adjacent to your property. The contractor will now be required to provide ongoing maintenance, including watering of the sodded areas until Friday, August 25, 2023. After the 60 days, you will be notified by letter that the sod has been accepted, that it will no longer be subject to a warranty, and that ongoing care and maintenance will become the responsibility of the property owners.

    In an effort to ensure the newly placed sod is given the best chance to root and survive the contractor will be subject to several requirements that will include:

    • Daily watering for the first 7 days after the sod is placed.
    • Ongoing watering during the first 60 days as needed: and
    • Fertilizing with a granulated fertilizer and aeration

    The city will inspect the condition of the newly sodded area at the end of 60 days. The contractor will be required to replace any deteriorated sod noted at the time of inspection. After this inspection and the replacement of any deteriorated sod, the care and maintenance of the sod will become the homeowner’s responsibility.

    After construction, depression settlement may occur, meaning the soil over the area that was dug up had settled. Should depression occur, rectification of the depression will occur during the project two-year maintenance period.

    Please note, new sod may take up to two years to fully root and establish. The weather, sun exposure and such can affect the establishment and health of young sod. We encourage property owners to continue periodic watering (adhering to the Region of Waterloo water use by-law) and care and maintenance after the end of the sod warranty.

    If you have any questions concerning this matter, please do not hesitate to contact the city’s Project Manager at phone number 519-741-2200 ext. 7132 or email at licinio.costa@kitchener.ca.

    If you would like to receive updates for this project as they become available, please subscribe and you will be added to the email list for updates on this project.

  • Introduction and Precondition Survey

    Share Introduction and Precondition Survey on Facebook Share Introduction and Precondition Survey on Twitter Share Introduction and Precondition Survey on Linkedin Email Introduction and Precondition Survey link

    We have awarded J. Weber Contracting the contract for reconstruction work on Second Avenue (Connaught Street to Kingsway Drive). Construction is scheduled to start on/or about April 3, 2023 with an anticipated completion on/or about August 31, 2023.

    The City of Kitchener has retained an Engineering Consultant to act as Project Manager for this project and they should be your first point of contact should you have any questions, concerns or require special access to your residence during construction. Their contact information can be found in the contact list provided at the end of this letter. However, as the City Project Manager Licinio Costa remains a key point of contact; contact information has been provided in the contact list. A Construction Inspector will be on site daily while the contractor is working. Should you have any questions or concerns while the work is in progress, the Construction Inspector can be identified by the white hardhat and can be approached at any time or contacted using the number provided in the contact list. Should you experience an after-hours emergency, please contact the 24 hour Contact Centre at 519-741-2345.

    The Contractor will start the project with the setup of their temporary watermain and by completing the pre-condition survey.

    Pre-Condition Survey of Structures

    On heavy construction projects, it is the City of Kitchener’s standard practice to offer to inspect any buildings that might be affected by construction activities before construction starts. If during or after construction residents/tenants experience any concerns with their property, the information from the pre-construction survey will prove very helpful in quickly and accurately resolving any claims, should they arise.

    The pre-condition survey will be conducted by Oza Inspection Limited and if they haven’t already, they will be contacting you within the next few days to arrange for this survey. This survey includes an inspection of the interior and exterior of each property to document the existing condition prior to construction. In large high rise apartment buildings the ground floor area will be inspected, but the individual apartment units above will not be inspected.

    We appreciate that some tenants/residents may not want a pre-condition survey of their home and we would like to stress that you are under no obligation to do so. Should this be the case, please advise the representative when they call

    You will likely feel some vibrations during the routine operation of construction equipment; however, studies have shown that these vibrations are much less severe than the vibration level likely to cause structural damage. We do recommend that you remove light, fragile or delicate objects from shelves when construction activity is taking place adjacent to your property.

    Should you experience any problems during construction, please contact me immediately and I’ll address or direct your concern to the contractor if needed. If immediate action is needed, such as an issue with your services and City Staff or Representatives are not immediately available, you are welcome to contact the contractor directly.

    Should situations arise during or after this construction project, the following contact information and telephone numbers are provided for your convenience.

    On Street Parking

    During reconstruction, temporary parking permits will be issued to displaced residents to allow on-street parking when needed. The permits will list streets for parking options as you will be permitted to park longer than 3 hours and overnight. Permits are to be displayed on the dash of your vehicle. Ensure that your vehicle is parked in permitted areas only and that you do not interfere with any construction operations.

    We communicate with the Bylaw Enforcement team to ensure residents displaced by construction are noted, although illegal parking and/or safety related issues will continue to be enforced. If you require parking enforcement, please contact 519-741-2345. If you have any inquiries, please speak to the site inspector for further direction

    Contacts

    City of Kitchener Project Manager

    Licinio Costa – 519-741-2200 ext. 7132

    Consultant Project Manager – Aecom

    Steve Collie – 519-650-8665

    Consultant Construction Inspector – Aecom

    Vincent Bruno – Vincent.bruno@aecom.com

    Contractor – J. Weber Contracting

    Murray Childerhose – 519-648-3302

    Corporate Contact Centre (24 hour)

    519-741-2345

    We appreciate your patience and understanding during this project.

  • Final Project Design Details

    Share Final Project Design Details on Facebook Share Final Project Design Details on Twitter Share Final Project Design Details on Linkedin Email Final Project Design Details link

    As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff has scheduled road, sewer and watermain improvements in your neighbourhood on the street listed above.

    These improvements are scheduled to begin, on or about, April 3, 2023, with an estimated completion date on or about September 15, 2023. You will be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.

    The specific improvements scheduled for these streets are:

    Upgrade the existing storm sewer, sanitary sewer and water mains.

    • Replace existing sanitary, storm and water services from the new mains to the property line.
    • Replace curb and gutter, and sidewalks.
    • Upgrade the asphalt roadway.
    • Replace all driveway ramp entrances in concrete

    These improvements are being done to upgrade the existing, deteriorated underground services and above ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.

    Presentation materials were shared with the public last year outlining the details of the proposed improvements to these streets. Updated details have been posted for viewing of all members of the public including owners and residents that will be directly affected by the proposed improvements. For more information regarding this project please visit Engagewr.ca/RoadReconstruction. If you would like to receive updates for this project as they become available, please subscribe and you will be added to the email list for updates on this project.

    If you have any questions and/or concerns about this project, please feel free to contact either of the project managers, listed below.

  • Construction postponed to 2023

    Share Construction postponed to 2023 on Facebook Share Construction postponed to 2023 on Twitter Share Construction postponed to 2023 on Linkedin Email Construction postponed to 2023 link

    The road reconstruction on Second Avenue from Kingsway Drive to Connaught Street has been postponed to 2023. To get updates by email about this project, please use the 'Subscribe' button.

  • Letter to Residents

    Share Letter to Residents on Facebook Share Letter to Residents on Twitter Share Letter to Residents on Linkedin Email Letter to Residents link

    As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff has scheduled road and sewer improvements in your neighbourhood.

    These improvements are tentatively scheduled to begin, on or about, May 2, 2022, with an estimated completion date on or about September 30, 2022 subject to Council budget approval in early 2022. Once a schedule for the construction has been confirmed you will be notified. You will also be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.

    The specific improvements scheduled for this street are:

    Upgrade the existing storm sewer, sanitary sewer and water mains.

    • Replace existing sanitary and water services from the new mains to the property line.
    • Curb and gutter, and sidewalks will be installed.
    • Upgrade the asphalt roadway.
    • Replace all driveway ramp entrances in concrete.

    The City is proposing some elements of the “Complete Streets” approach including a narrower roadway and a wider sidewalk on the east side of the street. The roadway asphalt width will be reduced from 10.0m to 7.0m. Parking will be allowed as it is currently allowed. The width of the sidewalk on the east side of the street will be increased from the existing width of 1.5m to 1.8m.

    These improvements are being done to upgrade the existing, deteriorated underground services and above-ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.

    In order to carry out these improvements, it will be necessary to close this street to through traffic. Prior to any road closure, signs will be posted on the approaching streets advising motorists of the date and the duration of the closure.

    Pedestrian access will be maintained to all properties at all times and vehicular access to all properties within the construction area will be maintained for as long as possible. On-street parking permits, which will allow parking on adjacent side streets, will be hand-delivered to affected homes before vehicular access is cut off.