The construction is now complete, and the project has entered the maintenance phase. This means we will inspect all aspects of the work done to ensure that it meets our standards. We will also address any deficiencies. Once this phase is complete, we will add a final layer of surface asphalt. This is usually about two years from the start of maintenance. If you have any questions or concerns, please contact us at 519-741-2345 (TTY:1-866-969-9994) or engineering@kitchener.ca
As part of the City of Kitchener’s ongoing efforts to provide exceptional service, staff has scheduled road and sewer improvements in your neighbourhood.
The specific improvements scheduled for this street are:
- Upgrade the existing storm sewer, sanitary sewer and water mains.
- Replace existing sanitary and water services from the new mains to the property line.
- Curb and gutter, and sidewalk on one side will be installed.
- Upgrade the asphalt roadway.
- Replace all driveway ramp entrances
These improvements are scheduled to begin, on or about, May 2022, with an estimated completion in 2023. You will be notified closer to the date construction is scheduled to start on your section of the street, and also how long access to your driveway will be affected.
Please read theInformation Package for more details about how this construction may affect you.
All residents are also invited to review the Project Information Boards for more information.
Progress and major milestones will be posted on this project page.
Updates
Update on project status for Stage 2
April 12, 2023Update on project status for Stage 1
April 12, 2023